HIVE Grand Falls campus and BUZZ conversion

HIVE Digital Technologies / BUZZ HPC · Grand Falls, New Brunswick

Record nb-hive-grandfalls · 2026-10-06-83c11c799ab4-public-2026-10-06

Historical published edition. Do not treat these as newer or additional facts. Evidence reviewed through 2026-10-06. Edition publication date: 2026-10-06.

Research record, not a building count. Campus and phase overlap may exist; do not add capacity values.

Current record profile · This edition’s record JSON · Edition overview

Identity provenance

Lifecycle

Conversion planned

In May 2026, HIVE said its Grand Falls mining campus was energized while BUZZ advanced an AI/HPC conversion; AI commissioning was not announced.

Evidence date
2026-05-08
Checked
2026-10-05
Scope
Facility
Evidence type
Reported
Status describes
Facility or project lifecycle
Citation text (select to copy)

Clarion Solutions. HIVE Grand Falls campus and BUZZ conversion. Canadian Data Centre Atlas. Record nb-hive-grandfalls; claim pub-quebec-east-nb-hive-grandfalls-1. Edition 2026-10-06-83c11c799ab4-public-2026-10-06 (publication date: 2026-10-06); evidence review through 2026-10-06. Claim evidence date: 2026-05-08; source checked: 2026-10-05. https://data.clarionsolutions.ca/canada-data-centres/editions/2026-10-06-83c11c799ab4-public-2026-10-06/records/nb-hive-grandfalls/#claim-pub-quebec-east-nb-hive-grandfalls-1

Cite the linked primary evidence as well. Publication and access dates do not establish current operations.

Capacity

Reported

The issuer reported 70 MW of energized gross load at Grand Falls.

Evidence date
2026-05-08
Checked
2026-10-05
Scope
Facility
Evidence type
Reported
Status describes
Reported capacity
Quantity type
Facility power
Basis
issuer-reported energized gross load; not measured demand or AI IT load
Reported quantity
70 MW
Citation text (select to copy)

Clarion Solutions. HIVE Grand Falls campus and BUZZ conversion. Canadian Data Centre Atlas. Record nb-hive-grandfalls; claim pub-quebec-east-nb-hive-grandfalls-2. Edition 2026-10-06-83c11c799ab4-public-2026-10-06 (publication date: 2026-10-06); evidence review through 2026-10-06. Claim evidence date: 2026-05-08; source checked: 2026-10-05. https://data.clarionsolutions.ca/canada-data-centres/editions/2026-10-06-83c11c799ab4-public-2026-10-06/records/nb-hive-grandfalls/#claim-pub-quebec-east-nb-hive-grandfalls-2

Cite the linked primary evidence as well. Publication and access dates do not establish current operations.

Capacity

Planned

BUZZ targeted a 50 MW AI/HPC conversion at the existing campus.

Evidence date
2026-05-08
Checked
2026-10-05
Scope
Facility
Evidence type
Reported
Status describes
Reported capacity
Quantity type
Unspecified
Basis
conversion target; gross-versus-IT basis not stated
Reported quantity
50 MW
Citation text (select to copy)

Clarion Solutions. HIVE Grand Falls campus and BUZZ conversion. Canadian Data Centre Atlas. Record nb-hive-grandfalls; claim pub-quebec-east-nb-hive-grandfalls-3. Edition 2026-10-06-83c11c799ab4-public-2026-10-06 (publication date: 2026-10-06); evidence review through 2026-10-06. Claim evidence date: 2026-05-08; source checked: 2026-10-05. https://data.clarionsolutions.ca/canada-data-centres/editions/2026-10-06-83c11c799ab4-public-2026-10-06/records/nb-hive-grandfalls/#claim-pub-quebec-east-nb-hive-grandfalls-3

Cite the linked primary evidence as well. Publication and access dates do not establish current operations.

Capacity

Reported

HIVE described an owned 80 MW substation serving the campus.

Evidence date
2025-11-03
Checked
2026-10-05
Scope
Facility
Evidence type
Reported
Status describes
Reported capacity
Quantity type
Utility supply
Basis
substation rating; overlaps campus power and is not additive
Reported quantity
80 MW
Citation text (select to copy)

Clarion Solutions. HIVE Grand Falls campus and BUZZ conversion. Canadian Data Centre Atlas. Record nb-hive-grandfalls; claim pub-quebec-east-nb-hive-grandfalls-4. Edition 2026-10-06-83c11c799ab4-public-2026-10-06 (publication date: 2026-10-06); evidence review through 2026-10-06. Claim evidence date: 2025-11-03; source checked: 2026-10-05. https://data.clarionsolutions.ca/canada-data-centres/editions/2026-10-06-83c11c799ab4-public-2026-10-06/records/nb-hive-grandfalls/#claim-pub-quebec-east-nb-hive-grandfalls-4

Cite the linked primary evidence as well. Publication and access dates do not establish current operations.

Power

Reported

HIVE characterizes Grand Falls power as hydroelectric; this is an issuer environmental description, not proof of exclusive physical hydro delivery.

Evidence date
2025-11-03
Checked
2026-10-05
Scope
Facility
Evidence type
Reported
Status describes
Power configuration
Citation text (select to copy)

Clarion Solutions. HIVE Grand Falls campus and BUZZ conversion. Canadian Data Centre Atlas. Record nb-hive-grandfalls; claim pub-quebec-east-nb-hive-grandfalls-5. Edition 2026-10-06-83c11c799ab4-public-2026-10-06 (publication date: 2026-10-06); evidence review through 2026-10-06. Claim evidence date: 2025-11-03; source checked: 2026-10-05. https://data.clarionsolutions.ca/canada-data-centres/editions/2026-10-06-83c11c799ab4-public-2026-10-06/records/nb-hive-grandfalls/#claim-pub-quebec-east-nb-hive-grandfalls-5

Cite the linked primary evidence as well. Publication and access dates do not establish current operations.

Ownership

Historical

The 2021 acquisition announcement identifies HIVE Atlantic Datacentres Ltd., formerly GPU Atlantic Inc., as the acquired facility-owning subsidiary.

Evidence date
2021-04-19
Checked
2026-10-05
Scope
Facility
Evidence type
Reported
Status describes
Ownership operator or developer relationship
Citation text (select to copy)

Clarion Solutions. HIVE Grand Falls campus and BUZZ conversion. Canadian Data Centre Atlas. Record nb-hive-grandfalls; claim pub-quebec-east-nb-hive-grandfalls-6. Edition 2026-10-06-83c11c799ab4-public-2026-10-06 (publication date: 2026-10-06); evidence review through 2026-10-06. Claim evidence date: 2021-04-19; source checked: 2026-10-05. https://data.clarionsolutions.ca/canada-data-centres/editions/2026-10-06-83c11c799ab4-public-2026-10-06/records/nb-hive-grandfalls/#claim-pub-quebec-east-nb-hive-grandfalls-6

Cite the linked primary evidence as well. Publication and access dates do not establish current operations.

Connectivity

Contracted not delivery verified

HIVE contracted a carrier fibre upgrade, including multiple 100/400 Gbps wavelengths, for approximately US$3.1 million over five years; delivery was expected from Q3 2026.

Evidence date
2026-05-08
Checked
2026-10-05
Scope
Facility
Evidence type
Reported
Status describes
Connectivity service or plan
Citation text (select to copy)

Clarion Solutions. HIVE Grand Falls campus and BUZZ conversion. Canadian Data Centre Atlas. Record nb-hive-grandfalls; claim pub-quebec-east-nb-hive-grandfalls-7. Edition 2026-10-06-83c11c799ab4-public-2026-10-06 (publication date: 2026-10-06); evidence review through 2026-10-06. Claim evidence date: 2026-05-08; source checked: 2026-10-05. https://data.clarionsolutions.ca/canada-data-centres/editions/2026-10-06-83c11c799ab4-public-2026-10-06/records/nb-hive-grandfalls/#claim-pub-quebec-east-nb-hive-grandfalls-7

Cite the linked primary evidence as well. Publication and access dates do not establish current operations.