DMG Christina Lake data centre
DMG Blockchain Solutions · Christina Lake, British Columbia
Record bc-dmg-christina · 2026-10-06-83c11c799ab4-public-2026-10-06
Historical published edition. Do not treat these as newer or additional facts. Evidence reviewed through 2026-10-06. Edition publication date: 2026-10-06.
Research record, not a building count. Campus and phase overlap may exist; do not add capacity values.
Current record profile · This edition’s record JSON · Edition overview
Identity provenance
- city: Issuer press release via GlobeNewswire
- disposition: Issuer press release via GlobeNewswire
- name: Issuer press release via GlobeNewswire
- operator: Issuer press release via GlobeNewswire
- province: Issuer press release via GlobeNewswire
- record_kind: Issuer press release via GlobeNewswire
Location
ReportedChristina Lake, British Columbia. City or regional reference only; no facility coordinates are published.
- Evidence date
- Undated source
- Checked
- 2026-10-05
- Scope
- Facility
- Evidence type
- Reported
- Status describes
- Published location reference
- DMG Blockchain Solutions Provides Update on its Christina · Issuer press release via GlobeNewswire
Permanent claim link · Claim pub-bc-dmg-christina-review-1
Citation text (select to copy)
Clarion Solutions. DMG Christina Lake data centre. Canadian Data Centre Atlas. Record bc-dmg-christina; claim pub-bc-dmg-christina-review-1. Edition 2026-10-06-83c11c799ab4-public-2026-10-06 (publication date: 2026-10-06); evidence review through 2026-10-06. Claim evidence date: undated; source checked: 2026-10-05. https://data.clarionsolutions.ca/canada-data-centres/editions/2026-10-06-83c11c799ab4-public-2026-10-06/records/bc-dmg-christina/#claim-pub-bc-dmg-christina-review-1
Cite the linked primary evidence as well. Publication and access dates do not establish current operations.
Lifecycle
Conversion proposedDMG describes an existing mining facility being considered for AI conversion. Its September update says the proposed AI tenancy is not yet under a definitive agreement.
- Evidence date
- 2026-09-14
- Checked
- 2026-10-05
- Scope
- Facility
- Evidence type
- Reported
- Status describes
- Facility or project lifecycle
- DMG Blockchain Solutions Provides Update on its Christina · Issuer press release via GlobeNewswire
Permanent claim link · Claim pub-bc-dmg-christina-review-2
Citation text (select to copy)
Clarion Solutions. DMG Christina Lake data centre. Canadian Data Centre Atlas. Record bc-dmg-christina; claim pub-bc-dmg-christina-review-2. Edition 2026-10-06-83c11c799ab4-public-2026-10-06 (publication date: 2026-10-06); evidence review through 2026-10-06. Claim evidence date: 2026-09-14; source checked: 2026-10-05. https://data.clarionsolutions.ca/canada-data-centres/editions/2026-10-06-83c11c799ab4-public-2026-10-06/records/bc-dmg-christina/#claim-pub-bc-dmg-christina-review-2
Cite the linked primary evidence as well. Publication and access dates do not establish current operations.
Capacity
Mixed existing and proposedDMG confirms 75 MW utility capacity, comprising 15 MW firm and 60 MW curtailable, after contracting an additional 10 MW. A separate 150 MW firm application, 50 MW critical-IT tenant LOI and possible 60 MW critical-IT addition remain conditional. None may be summed or treated as commissioned AI IT capacity.
- Evidence date
- 2026-09-14
- Checked
- 2026-10-05
- Scope
- Facility
- Evidence type
- Reported
- Status describes
- Capacity at stated basis and scope
- Quantity type
- Utility supply
- Basis
- approved
- DMG Blockchain Solutions Provides Update on its Christina · Issuer press release via GlobeNewswire
Permanent claim link · Claim pub-bc-dmg-christina-review-3
Citation text (select to copy)
Clarion Solutions. DMG Christina Lake data centre. Canadian Data Centre Atlas. Record bc-dmg-christina; claim pub-bc-dmg-christina-review-3. Edition 2026-10-06-83c11c799ab4-public-2026-10-06 (publication date: 2026-10-06); evidence review through 2026-10-06. Claim evidence date: 2026-09-14; source checked: 2026-10-05. https://data.clarionsolutions.ca/canada-data-centres/editions/2026-10-06-83c11c799ab4-public-2026-10-06/records/bc-dmg-christina/#claim-pub-bc-dmg-christina-review-3
Cite the linked primary evidence as well. Publication and access dates do not establish current operations.
Connectivity
ContractedDMG says it contracted two providers for two 100 Gbps fibre paths. A possible third path and upgrades to 400 Gbps remain options; activation dates are not disclosed.
- Evidence date
- 2026-09-14
- Checked
- 2026-10-05
- Scope
- Facility
- Evidence type
- Reported
- Status describes
- Connectivity infrastructure or service
- DMG Blockchain Solutions Provides Update on its Christina · Issuer press release via GlobeNewswire
Permanent claim link · Claim pub-bc-dmg-christina-review-4
Citation text (select to copy)
Clarion Solutions. DMG Christina Lake data centre. Canadian Data Centre Atlas. Record bc-dmg-christina; claim pub-bc-dmg-christina-review-4. Edition 2026-10-06-83c11c799ab4-public-2026-10-06 (publication date: 2026-10-06); evidence review through 2026-10-06. Claim evidence date: 2026-09-14; source checked: 2026-10-05. https://data.clarionsolutions.ca/canada-data-centres/editions/2026-10-06-83c11c799ab4-public-2026-10-06/records/bc-dmg-christina/#claim-pub-bc-dmg-christina-review-4
Cite the linked primary evidence as well. Publication and access dates do not establish current operations.
Commercial
Letter of intentThe potential 50 MW critical-IT customer remains unnamed and its definitive colocation agreement is unresolved in the September update.
- Evidence date
- 2026-09-14
- Checked
- 2026-10-05
- Scope
- Facility
- Evidence type
- Reported
- Status describes
- Commercial disclosure or relationship
- DMG Blockchain Solutions Provides Update on its Christina · Issuer press release via GlobeNewswire
Permanent claim link · Claim pub-bc-dmg-christina-review-5
Citation text (select to copy)
Clarion Solutions. DMG Christina Lake data centre. Canadian Data Centre Atlas. Record bc-dmg-christina; claim pub-bc-dmg-christina-review-5. Edition 2026-10-06-83c11c799ab4-public-2026-10-06 (publication date: 2026-10-06); evidence review through 2026-10-06. Claim evidence date: 2026-09-14; source checked: 2026-10-05. https://data.clarionsolutions.ca/canada-data-centres/editions/2026-10-06-83c11c799ab4-public-2026-10-06/records/bc-dmg-christina/#claim-pub-bc-dmg-christina-review-5
Cite the linked primary evidence as well. Publication and access dates do not establish current operations.
Ownership
ReportedThe reviewed source identifies DMG Blockchain Solutions in the operator or development role. This does not establish title to the underlying land.
- Evidence date
- Undated source
- Checked
- 2026-10-05
- Scope
- Facility
- Evidence type
- Reported
- Status describes
- Ownership operator or developer relationship
- DMG Blockchain Solutions Provides Update on its Christina · Issuer press release via GlobeNewswire
Permanent claim link · Claim pub-bc-dmg-christina-review-6
Citation text (select to copy)
Clarion Solutions. DMG Christina Lake data centre. Canadian Data Centre Atlas. Record bc-dmg-christina; claim pub-bc-dmg-christina-review-6. Edition 2026-10-06-83c11c799ab4-public-2026-10-06 (publication date: 2026-10-06); evidence review through 2026-10-06. Claim evidence date: undated; source checked: 2026-10-05. https://data.clarionsolutions.ca/canada-data-centres/editions/2026-10-06-83c11c799ab4-public-2026-10-06/records/bc-dmg-christina/#claim-pub-bc-dmg-christina-review-6
Cite the linked primary evidence as well. Publication and access dates do not establish current operations.