CLARION Data projects

Version-specific research record

WhiteFiber / Enovum MTL-3

WhiteFiber / Enovum Data Centers · Saint-Jérôme, Quebec

Record QC-WHITEFIBER-MTL3 · 2026-10-06-83c11c799ab4-public-2026-10-06

Historical published edition. Do not treat these as newer or additional facts. Evidence reviewed through 2026-10-06. Edition publication date: 2026-10-06.

Research record, not a building count. Campus and phase overlap may exist; do not add capacity values.

Current record profile · This edition’s record JSON · Edition overview

Identity provenance

Lifecycle

Reported operating

The August 2026 filing states that MTL-3 became operational in November 2025; WhiteFiber acquired the Saint-Jérôme property in May 2026.

Evidence date
2026-08-12
Checked
2026-10-05
Scope
Facility
Evidence type
Reported
Status describes
Facility or project lifecycle
Citation text (select to copy)

Clarion Solutions. WhiteFiber / Enovum MTL-3. Canadian Data Centre Atlas. Record QC-WHITEFIBER-MTL3; claim pub-quebec-east-QC-WHITEFIBER-MTL3-1. Edition 2026-10-06-83c11c799ab4-public-2026-10-06 (publication date: 2026-10-06); evidence review through 2026-10-06. Claim evidence date: 2026-08-12; source checked: 2026-10-05. https://data.clarionsolutions.ca/canada-data-centres/editions/2026-10-06-83c11c799ab4-public-2026-10-06/records/QC-WHITEFIBER-MTL3/#claim-pub-quebec-east-QC-WHITEFIBER-MTL3-1

Cite the linked primary evidence as well. Publication and access dates do not establish current operations.

Capacity

Reported

The filing describes MTL-3 as 7 MW gross.

Evidence date
2026-08-12
Checked
2026-10-05
Scope
Facility
Evidence type
Reported
Status describes
Reported capacity
Quantity type
Facility power
Basis
gross facility rating; not equivalent to IT load or measured demand
Reported quantity
7 MW
Citation text (select to copy)

Clarion Solutions. WhiteFiber / Enovum MTL-3. Canadian Data Centre Atlas. Record QC-WHITEFIBER-MTL3; claim pub-quebec-east-QC-WHITEFIBER-MTL3-2. Edition 2026-10-06-83c11c799ab4-public-2026-10-06 (publication date: 2026-10-06); evidence review through 2026-10-06. Claim evidence date: 2026-08-12; source checked: 2026-10-05. https://data.clarionsolutions.ca/canada-data-centres/editions/2026-10-06-83c11c799ab4-public-2026-10-06/records/QC-WHITEFIBER-MTL3/#claim-pub-quebec-east-QC-WHITEFIBER-MTL3-2

Cite the linked primary evidence as well. Publication and access dates do not establish current operations.

Capacity

Reported

MTL-3’s Cerebras contract is for 5 MW IT load, within its 7 MW gross design.

Evidence date
2026-08-12
Checked
2026-10-05
Scope
Facility
Evidence type
Reported
Status describes
Reported capacity
Quantity type
It load
Basis
tenant-contracted IT capacity, not incremental to gross facility power
Reported quantity
5 MW
Citation text (select to copy)

Clarion Solutions. WhiteFiber / Enovum MTL-3. Canadian Data Centre Atlas. Record QC-WHITEFIBER-MTL3; claim pub-quebec-east-QC-WHITEFIBER-MTL3-3. Edition 2026-10-06-83c11c799ab4-public-2026-10-06 (publication date: 2026-10-06); evidence review through 2026-10-06. Claim evidence date: 2026-08-12; source checked: 2026-10-05. https://data.clarionsolutions.ca/canada-data-centres/editions/2026-10-06-83c11c799ab4-public-2026-10-06/records/QC-WHITEFIBER-MTL3/#claim-pub-quebec-east-QC-WHITEFIBER-MTL3-3

Cite the linked primary evidence as well. Publication and access dates do not establish current operations.

Cooling

Reported

WhiteFiber’s MTL-3 page describes direct-to-chip liquid cooling, N+1 systems and carrier-neutral connectivity; exact physical route diversity is not independently established.

Evidence date
Undated source
Checked
2026-10-05
Scope
Facility
Evidence type
Reported
Status describes
Cooling configuration
Citation text (select to copy)

Clarion Solutions. WhiteFiber / Enovum MTL-3. Canadian Data Centre Atlas. Record QC-WHITEFIBER-MTL3; claim pub-quebec-east-QC-WHITEFIBER-MTL3-4. Edition 2026-10-06-83c11c799ab4-public-2026-10-06 (publication date: 2026-10-06); evidence review through 2026-10-06. Claim evidence date: undated; source checked: 2026-10-05. https://data.clarionsolutions.ca/canada-data-centres/editions/2026-10-06-83c11c799ab4-public-2026-10-06/records/QC-WHITEFIBER-MTL3/#claim-pub-quebec-east-QC-WHITEFIBER-MTL3-4

Cite the linked primary evidence as well. Publication and access dates do not establish current operations.

Commercial

Reported

The filing states Cerebras billing began November 1, 2025 at C$1.4 million monthly under a five-year contract; this is tenant-specific, not market pricing.

Evidence date
2026-08-12
Checked
2026-10-05
Scope
Facility
Evidence type
Reported
Status describes
Commercial disclosure
Citation text (select to copy)

Clarion Solutions. WhiteFiber / Enovum MTL-3. Canadian Data Centre Atlas. Record QC-WHITEFIBER-MTL3; claim pub-quebec-east-QC-WHITEFIBER-MTL3-5. Edition 2026-10-06-83c11c799ab4-public-2026-10-06 (publication date: 2026-10-06); evidence review through 2026-10-06. Claim evidence date: 2026-08-12; source checked: 2026-10-05. https://data.clarionsolutions.ca/canada-data-centres/editions/2026-10-06-83c11c799ab4-public-2026-10-06/records/QC-WHITEFIBER-MTL3/#claim-pub-quebec-east-QC-WHITEFIBER-MTL3-5

Cite the linked primary evidence as well. Publication and access dates do not establish current operations.