BUZZ HPC 320 MW AI gigafactory

BUZZ High Performance Computing / HIVE · Greater Toronto Area, Ontario

Record on-113 · 2026-10-06-83c11c799ab4-public-2026-10-07

Current selected data edition. Evidence reviewed through 2026-10-06. Edition publication date: 2026-10-07.

Research record, not a building count. Campus and phase overlap may exist; do not add capacity values.

Current record profile · This edition’s record JSON · Edition overview

Identity provenance

Lifecycle

Planned

HIVE’s May 2026 announcement targets second-half 2027 for the planned Greater Toronto Area AI campus.

Evidence date
2026-05-18
Checked
2026-10-05
Scope
Facility
Evidence type
Reported
Status describes
Facility or project lifecycle
Citation text (select to copy)

Clarion Solutions. BUZZ HPC 320 MW AI gigafactory. Canadian Data Centre Atlas. Record on-113; claim pub-ontario_a-on-113-1. Edition 2026-10-06-83c11c799ab4-public-2026-10-07 (publication date: 2026-10-07); evidence review through 2026-10-06. Claim evidence date: 2026-05-18; source checked: 2026-10-05. https://data.clarionsolutions.ca/canada-data-centres/editions/2026-10-06-83c11c799ab4-public-2026-10-07/records/on-113/#claim-pub-ontario_a-on-113-1

Cite the linked primary evidence as well. Publication and access dates do not establish current operations.

Capacity

Planned

The issuer reports a 320 MW utility-power allocation for the acquired site. The filing does not provide an executed utility agreement or establish energized IT capacity.

Evidence date
2026-05-18
Checked
2026-10-05
Scope
Campus
Evidence type
Reported
Status describes
Capacity at stated basis and scope
Quantity type
Utility
Basis
issuer-reported allocation; unverified energization
Reported quantity
320 MW
Citation text (select to copy)

Clarion Solutions. BUZZ HPC 320 MW AI gigafactory. Canadian Data Centre Atlas. Record on-113; claim pub-ontario_a-on-113-2. Edition 2026-10-06-83c11c799ab4-public-2026-10-07 (publication date: 2026-10-07); evidence review through 2026-10-06. Claim evidence date: 2026-05-18; source checked: 2026-10-05. https://data.clarionsolutions.ca/canada-data-centres/editions/2026-10-06-83c11c799ab4-public-2026-10-07/records/on-113/#claim-pub-ontario_a-on-113-2

Cite the linked primary evidence as well. Publication and access dates do not establish current operations.

Cooling

Planned

The design calls for Ontario-grid electricity and closed-loop cooling with a no-water-use approach; these are project intentions, not installed-system evidence.

Evidence date
2026-05-18
Checked
2026-10-05
Scope
Facility
Evidence type
Reported
Status describes
Power supply or backup configuration
Citation text (select to copy)

Clarion Solutions. BUZZ HPC 320 MW AI gigafactory. Canadian Data Centre Atlas. Record on-113; claim pub-ontario_a-on-113-3. Edition 2026-10-06-83c11c799ab4-public-2026-10-07 (publication date: 2026-10-07); evidence review through 2026-10-06. Claim evidence date: 2026-05-18; source checked: 2026-10-05. https://data.clarionsolutions.ca/canada-data-centres/editions/2026-10-06-83c11c799ab4-public-2026-10-07/records/on-113/#claim-pub-ontario_a-on-113-3

Cite the linked primary evidence as well. Publication and access dates do not establish current operations.

Hardware

Planned

The full-buildout design targets more than 100,000 GPUs; models, procurement and installed inventory are not established.

Evidence date
2026-05-18
Checked
2026-10-05
Scope
Campus
Evidence type
Reported
Status describes
Hardware deployment procurement or support
Citation text (select to copy)

Clarion Solutions. BUZZ HPC 320 MW AI gigafactory. Canadian Data Centre Atlas. Record on-113; claim pub-ontario_a-on-113-4. Edition 2026-10-06-83c11c799ab4-public-2026-10-07 (publication date: 2026-10-07); evidence review through 2026-10-06. Claim evidence date: 2026-05-18; source checked: 2026-10-05. https://data.clarionsolutions.ca/canada-data-centres/editions/2026-10-06-83c11c799ab4-public-2026-10-07/records/on-113/#claim-pub-ontario_a-on-113-4

Cite the linked primary evidence as well. Publication and access dates do not establish current operations.

Ownership

Reported

HIVE states that its BUZZ subsidiary acquired adjoining parcels of approximately 21 and 4 acres.

Evidence date
2026-05-18
Checked
2026-10-05
Scope
Facility
Evidence type
Reported
Status describes
Ownership operator or developer relationship
Citation text (select to copy)

Clarion Solutions. BUZZ HPC 320 MW AI gigafactory. Canadian Data Centre Atlas. Record on-113; claim pub-ontario_a-on-113-5. Edition 2026-10-06-83c11c799ab4-public-2026-10-07 (publication date: 2026-10-07); evidence review through 2026-10-06. Claim evidence date: 2026-05-18; source checked: 2026-10-05. https://data.clarionsolutions.ca/canada-data-centres/editions/2026-10-06-83c11c799ab4-public-2026-10-07/records/on-113/#claim-pub-ontario_a-on-113-5

Cite the linked primary evidence as well. Publication and access dates do not establish current operations.