BUZZ HPC 320 MW AI gigafactory

BUZZ High Performance Computing / HIVE · Greater Toronto Area, Ontario

Research record, not a building count. Campus and phase overlap may exist; do not add capacity values. Access dates do not establish fresh commissioning.

Identity and map provenance

No unique reviewed city reference. Intentionally unpinned.

Lifecycle

Planned

HIVE’s May 2026 announcement targets second-half 2027 for the planned Greater Toronto Area AI campus.

Evidence date
2026-05-18
Checked
2026-10-05
Scope
Facility
Evidence type
Reported
Status describes
Facility or project lifecycle

Capacity

Planned

The issuer reports a 320 MW utility-power allocation for the acquired site. The filing does not provide an executed utility agreement or establish energized IT capacity.

Evidence date
2026-05-18
Checked
2026-10-05
Scope
Campus
Evidence type
Reported
Status describes
Capacity at stated basis and scope
Quantity type
Utility
Basis
issuer-reported allocation; unverified energization
Reported quantity
320 MW

Cooling

Planned

The design calls for Ontario-grid electricity and closed-loop cooling with a no-water-use approach; these are project intentions, not installed-system evidence.

Evidence date
2026-05-18
Checked
2026-10-05
Scope
Facility
Evidence type
Reported
Status describes
Power supply or backup configuration

Hardware

Planned

The full-buildout design targets more than 100,000 GPUs; models, procurement and installed inventory are not established.

Evidence date
2026-05-18
Checked
2026-10-05
Scope
Campus
Evidence type
Reported
Status describes
Hardware deployment procurement or support

Ownership

Reported

HIVE states that its BUZZ subsidiary acquired adjoining parcels of approximately 21 and 4 acres.

Evidence date
2026-05-18
Checked
2026-10-05
Scope
Facility
Evidence type
Reported
Status describes
Ownership operator or developer relationship