Version-specific research record
Meta Sturgeon Data Centre / GLDC
Meta · Sturgeon County, Alberta
Record ab-meta-sturgeon · 2026-10-06-83c11c799ab4-public-2026-10-07
Current selected data edition. Evidence reviewed through 2026-10-06. Edition publication date: 2026-10-07.
Research record, not a building count. Campus and phase overlap may exist; do not add capacity values.
Current record profile · This edition’s record JSON · Edition overview
Identity provenance
- name: Meta, Sturgeon County, Pembina Pipeline filing on SEC EDGAR, Issuer press release via GlobeNewswire
- operator: Meta, Sturgeon County, Pembina Pipeline filing on SEC EDGAR, Issuer press release via GlobeNewswire
- province: Meta, Sturgeon County, Pembina Pipeline filing on SEC EDGAR, Issuer press release via GlobeNewswire
- city: Meta, Sturgeon County, Pembina Pipeline filing on SEC EDGAR, Issuer press release via GlobeNewswire
- record_kind: Meta, Sturgeon County, Pembina Pipeline filing on SEC EDGAR, Issuer press release via GlobeNewswire
- disposition: Meta, Sturgeon County, Pembina Pipeline filing on SEC EDGAR, Issuer press release via GlobeNewswire
Location
ReportedSturgeon County, Alberta. City or regional reference only; no facility coordinates are published.
- Evidence date
- Undated source
- Checked
- 2026-10-05
- Scope
- Facility
- Evidence type
- Reported
- Status describes
- Published location reference
- Breaking Ground on Meta’s First Data Center in Canada · Meta
- Heartland Activity Update · Sturgeon County
- Greenlight Electricity Centre final investment decision, 2 July 2026 · Pembina Pipeline filing on SEC EDGAR
- Capital Power Enters Long-term Energy Supply Agreement with · Issuer press release via GlobeNewswire
Permanent claim link · Claim pub-ab-meta-sturgeon-review-1
Citation text (select to copy)
Clarion Solutions. Meta Sturgeon Data Centre / GLDC. Canadian Data Centre Atlas. Record ab-meta-sturgeon; claim pub-ab-meta-sturgeon-review-1. Edition 2026-10-06-83c11c799ab4-public-2026-10-07 (publication date: 2026-10-07); evidence review through 2026-10-06. Claim evidence date: undated; source checked: 2026-10-05. https://data.clarionsolutions.ca/canada-data-centres/editions/2026-10-06-83c11c799ab4-public-2026-10-07/records/ab-meta-sturgeon/#claim-pub-ab-meta-sturgeon-review-1
Cite the linked primary evidence as well. Publication and access dates do not establish current operations.
Lifecycle
Under constructionMeta announced groundbreaking in July 2026. The county’s August update distinguishes site preparation from remaining building and safety permits.
- Evidence date
- 2026-08
- Checked
- 2026-10-05
- Scope
- Facility
- Evidence type
- Reported
- Status describes
- Facility or project lifecycle
- Breaking Ground on Meta’s First Data Center in Canada · Meta
- Heartland Activity Update · Sturgeon County
- Greenlight Electricity Centre final investment decision, 2 July 2026 · Pembina Pipeline filing on SEC EDGAR
- Capital Power Enters Long-term Energy Supply Agreement with · Issuer press release via GlobeNewswire
Permanent claim link · Claim pub-ab-meta-sturgeon-review-2
Citation text (select to copy)
Clarion Solutions. Meta Sturgeon Data Centre / GLDC. Canadian Data Centre Atlas. Record ab-meta-sturgeon; claim pub-ab-meta-sturgeon-review-2. Edition 2026-10-06-83c11c799ab4-public-2026-10-07 (publication date: 2026-10-07); evidence review through 2026-10-06. Claim evidence date: 2026-08; source checked: 2026-10-05. https://data.clarionsolutions.ca/canada-data-centres/editions/2026-10-06-83c11c799ab4-public-2026-10-07/records/ab-meta-sturgeon/#claim-pub-ab-meta-sturgeon-review-2
Cite the linked primary evidence as well. Publication and access dates do not establish current operations.
Capacity
PlannedMeta markets a 1 GW AI-focused data centre. The announcement does not define this as net server IT load.
- Evidence date
- 2026-07
- Checked
- 2026-10-05
- Scope
- Facility
- Evidence type
- Reported
- Status describes
- Capacity at stated basis and scope
- Quantity type
- Campus total
- Basis
- proposed
- Reported quantity
- 1000 MW
- Breaking Ground on Meta’s First Data Center in Canada · Meta
- Heartland Activity Update · Sturgeon County
- Greenlight Electricity Centre final investment decision, 2 July 2026 · Pembina Pipeline filing on SEC EDGAR
- Capital Power Enters Long-term Energy Supply Agreement with · Issuer press release via GlobeNewswire
Permanent claim link · Claim pub-ab-meta-sturgeon-review-3
Citation text (select to copy)
Clarion Solutions. Meta Sturgeon Data Centre / GLDC. Canadian Data Centre Atlas. Record ab-meta-sturgeon; claim pub-ab-meta-sturgeon-review-3. Edition 2026-10-06-83c11c799ab4-public-2026-10-07 (publication date: 2026-10-07); evidence review through 2026-10-06. Claim evidence date: 2026-07; source checked: 2026-10-05. https://data.clarionsolutions.ca/canada-data-centres/editions/2026-10-06-83c11c799ab4-public-2026-10-07/records/ab-meta-sturgeon/#claim-pub-ab-meta-sturgeon-review-3
Cite the linked primary evidence as well. Publication and access dates do not establish current operations.
Capacity
ApprovedThe county reports a 970 MW grid-connection approval. This is a connection quantity, not commissioned IT demand.
- Evidence date
- 2026-08
- Checked
- 2026-10-05
- Scope
- Facility
- Evidence type
- Reported
- Status describes
- Capacity at stated basis and scope
- Quantity type
- Utility supply
- Basis
- approved
- Reported quantity
- 970 MW
- Breaking Ground on Meta’s First Data Center in Canada · Meta
- Heartland Activity Update · Sturgeon County
- Greenlight Electricity Centre final investment decision, 2 July 2026 · Pembina Pipeline filing on SEC EDGAR
- Capital Power Enters Long-term Energy Supply Agreement with · Issuer press release via GlobeNewswire
Permanent claim link · Claim pub-ab-meta-sturgeon-review-4
Citation text (select to copy)
Clarion Solutions. Meta Sturgeon Data Centre / GLDC. Canadian Data Centre Atlas. Record ab-meta-sturgeon; claim pub-ab-meta-sturgeon-review-4. Edition 2026-10-06-83c11c799ab4-public-2026-10-07 (publication date: 2026-10-07); evidence review through 2026-10-06. Claim evidence date: 2026-08; source checked: 2026-10-05. https://data.clarionsolutions.ca/canada-data-centres/editions/2026-10-06-83c11c799ab4-public-2026-10-07/records/ab-meta-sturgeon/#claim-pub-ab-meta-sturgeon-review-4
Cite the linked primary evidence as well. Publication and access dates do not establish current operations.
Capacity
PlannedGreenlight’s dedicated supply project is a separate 932 MW gas-fired generating plant targeting the second half of 2030; it is not additional data-centre IT capacity.
- Evidence date
- 2026-07-02
- Checked
- 2026-10-05
- Scope
- Associated power plant · Greenlight initial plant
- Evidence type
- Reported
- Status describes
- Capacity at stated basis and scope
- Quantity type
- Generation
- Basis
- contracted
- Reported quantity
- 932 MW
- Breaking Ground on Meta’s First Data Center in Canada · Meta
- Heartland Activity Update · Sturgeon County
- Greenlight Electricity Centre final investment decision, 2 July 2026 · Pembina Pipeline filing on SEC EDGAR
- Capital Power Enters Long-term Energy Supply Agreement with · Issuer press release via GlobeNewswire
Permanent claim link · Claim pub-ab-meta-sturgeon-review-5
Citation text (select to copy)
Clarion Solutions. Meta Sturgeon Data Centre / GLDC. Canadian Data Centre Atlas. Record ab-meta-sturgeon; claim pub-ab-meta-sturgeon-review-5. Edition 2026-10-06-83c11c799ab4-public-2026-10-07 (publication date: 2026-10-07); evidence review through 2026-10-06. Claim evidence date: 2026-07-02; source checked: 2026-10-05. https://data.clarionsolutions.ca/canada-data-centres/editions/2026-10-06-83c11c799ab4-public-2026-10-07/records/ab-meta-sturgeon/#claim-pub-ab-meta-sturgeon-review-5
Cite the linked primary evidence as well. Publication and access dates do not establish current operations.
Power
PlannedThe supply plan includes dedicated gas generation and grid arrangements. Meta’s clean/renewable matching commitment is contractual accounting, not evidence that all physical electricity is gas-free.
- Evidence date
- Undated source
- Checked
- 2026-10-05
- Scope
- Facility
- Evidence type
- Reported
- Status describes
- Power supply or backup configuration
- Breaking Ground on Meta’s First Data Center in Canada · Meta
- Heartland Activity Update · Sturgeon County
- Greenlight Electricity Centre final investment decision, 2 July 2026 · Pembina Pipeline filing on SEC EDGAR
- Capital Power Enters Long-term Energy Supply Agreement with · Issuer press release via GlobeNewswire
Permanent claim link · Claim pub-ab-meta-sturgeon-review-6
Citation text (select to copy)
Clarion Solutions. Meta Sturgeon Data Centre / GLDC. Canadian Data Centre Atlas. Record ab-meta-sturgeon; claim pub-ab-meta-sturgeon-review-6. Edition 2026-10-06-83c11c799ab4-public-2026-10-07 (publication date: 2026-10-07); evidence review through 2026-10-06. Claim evidence date: undated; source checked: 2026-10-05. https://data.clarionsolutions.ca/canada-data-centres/editions/2026-10-06-83c11c799ab4-public-2026-10-07/records/ab-meta-sturgeon/#claim-pub-ab-meta-sturgeon-review-6
Cite the linked primary evidence as well. Publication and access dates do not establish current operations.
Cooling
PlannedMeta plans recirculating liquid cooling with dry heat rejection and no routine water consumption by the cooling system; commissioning has not been established.
- Evidence date
- 2026-07
- Checked
- 2026-10-05
- Scope
- Facility
- Evidence type
- Reported
- Status describes
- Cooling system at stated scope
- Breaking Ground on Meta’s First Data Center in Canada · Meta
- Heartland Activity Update · Sturgeon County
- Greenlight Electricity Centre final investment decision, 2 July 2026 · Pembina Pipeline filing on SEC EDGAR
- Capital Power Enters Long-term Energy Supply Agreement with · Issuer press release via GlobeNewswire
Permanent claim link · Claim pub-ab-meta-sturgeon-review-7
Citation text (select to copy)
Clarion Solutions. Meta Sturgeon Data Centre / GLDC. Canadian Data Centre Atlas. Record ab-meta-sturgeon; claim pub-ab-meta-sturgeon-review-7. Edition 2026-10-06-83c11c799ab4-public-2026-10-07 (publication date: 2026-10-07); evidence review through 2026-10-06. Claim evidence date: 2026-07; source checked: 2026-10-05. https://data.clarionsolutions.ca/canada-data-centres/editions/2026-10-06-83c11c799ab4-public-2026-10-07/records/ab-meta-sturgeon/#claim-pub-ab-meta-sturgeon-review-7
Cite the linked primary evidence as well. Publication and access dates do not establish current operations.
Capacity
ContractedCapital Power announced a greater-than-ten-year agreement for 250 MW of capacity and energy supporting Meta’s site, with a target start in the second half of 2028. It is fleet-backed supply, not another site-capacity increment.
- Evidence date
- 2026-07-08
- Checked
- 2026-10-05
- Scope
- Facility
- Evidence type
- Reported
- Status describes
- Capacity at stated basis and scope
- Quantity type
- Utility supply
- Basis
- contracted
- Reported quantity
- 250 MW · Separate source-reported quantities are not additive.
- Breaking Ground on Meta’s First Data Center in Canada · Meta
- Heartland Activity Update · Sturgeon County
- Greenlight Electricity Centre final investment decision, 2 July 2026 · Pembina Pipeline filing on SEC EDGAR
- Capital Power Enters Long-term Energy Supply Agreement with · Issuer press release via GlobeNewswire
Permanent claim link · Claim pub-ab-meta-sturgeon-review-8
Citation text (select to copy)
Clarion Solutions. Meta Sturgeon Data Centre / GLDC. Canadian Data Centre Atlas. Record ab-meta-sturgeon; claim pub-ab-meta-sturgeon-review-8. Edition 2026-10-06-83c11c799ab4-public-2026-10-07 (publication date: 2026-10-07); evidence review through 2026-10-06. Claim evidence date: 2026-07-08; source checked: 2026-10-05. https://data.clarionsolutions.ca/canada-data-centres/editions/2026-10-06-83c11c799ab4-public-2026-10-07/records/ab-meta-sturgeon/#claim-pub-ab-meta-sturgeon-review-8
Cite the linked primary evidence as well. Publication and access dates do not establish current operations.
Commercial
ContractedGreenlight’s announcement names Siemens equipment and an Aecon/Técnicas Reunidas construction arrangement for the associated power plant.
- Evidence date
- 2026-07-02
- Checked
- 2026-10-05
- Scope
- Associated power plant
- Evidence type
- Reported
- Status describes
- Commercial disclosure or relationship
- Breaking Ground on Meta’s First Data Center in Canada · Meta
- Heartland Activity Update · Sturgeon County
- Greenlight Electricity Centre final investment decision, 2 July 2026 · Pembina Pipeline filing on SEC EDGAR
- Capital Power Enters Long-term Energy Supply Agreement with · Issuer press release via GlobeNewswire
Permanent claim link · Claim pub-ab-meta-sturgeon-review-9
Citation text (select to copy)
Clarion Solutions. Meta Sturgeon Data Centre / GLDC. Canadian Data Centre Atlas. Record ab-meta-sturgeon; claim pub-ab-meta-sturgeon-review-9. Edition 2026-10-06-83c11c799ab4-public-2026-10-07 (publication date: 2026-10-07); evidence review through 2026-10-06. Claim evidence date: 2026-07-02; source checked: 2026-10-05. https://data.clarionsolutions.ca/canada-data-centres/editions/2026-10-06-83c11c799ab4-public-2026-10-07/records/ab-meta-sturgeon/#claim-pub-ab-meta-sturgeon-review-9
Cite the linked primary evidence as well. Publication and access dates do not establish current operations.
Ownership
ReportedThe reviewed source identifies Meta in the operator or development role. This does not establish title to the underlying land.
- Evidence date
- Undated source
- Checked
- 2026-10-05
- Scope
- Facility
- Evidence type
- Reported
- Status describes
- Ownership operator or developer relationship
- Breaking Ground on Meta’s First Data Center in Canada · Meta
- Heartland Activity Update · Sturgeon County
- Greenlight Electricity Centre final investment decision, 2 July 2026 · Pembina Pipeline filing on SEC EDGAR
- Capital Power Enters Long-term Energy Supply Agreement with · Issuer press release via GlobeNewswire
Permanent claim link · Claim pub-ab-meta-sturgeon-review-10
Citation text (select to copy)
Clarion Solutions. Meta Sturgeon Data Centre / GLDC. Canadian Data Centre Atlas. Record ab-meta-sturgeon; claim pub-ab-meta-sturgeon-review-10. Edition 2026-10-06-83c11c799ab4-public-2026-10-07 (publication date: 2026-10-07); evidence review through 2026-10-06. Claim evidence date: undated; source checked: 2026-10-05. https://data.clarionsolutions.ca/canada-data-centres/editions/2026-10-06-83c11c799ab4-public-2026-10-07/records/ab-meta-sturgeon/#claim-pub-ab-meta-sturgeon-review-10
Cite the linked primary evidence as well. Publication and access dates do not establish current operations.