Campus · Evidence reviewed 2026-10-06
Meta Sturgeon Data Centre / GLDC
Meta · Sturgeon County, Alberta
Research record, not a building count. Campus and phase overlap may exist; do not add capacity values. Access dates do not establish fresh commissioning.
Identity and map provenance
- Name: Meta, Sturgeon County, Pembina Pipeline filing on SEC EDGAR, Issuer press release via GlobeNewswire
- Operator: Meta, Sturgeon County, Pembina Pipeline filing on SEC EDGAR, Issuer press release via GlobeNewswire
- Province: Meta, Sturgeon County, Pembina Pipeline filing on SEC EDGAR, Issuer press release via GlobeNewswire
- City: Meta, Sturgeon County, Pembina Pipeline filing on SEC EDGAR, Issuer press release via GlobeNewswire
- Record kind: Meta, Sturgeon County, Pembina Pipeline filing on SEC EDGAR, Issuer press release via GlobeNewswire
- Disposition: Meta, Sturgeon County, Pembina Pipeline filing on SEC EDGAR, Issuer press release via GlobeNewswire
No unique reviewed city reference. Intentionally unpinned.
Location
ReportedSturgeon County, Alberta. City or regional reference only; no facility coordinates are published.
- Evidence date
- Undated source
- Checked
- 2026-10-05
- Scope
- Facility
- Evidence type
- Reported
- Status describes
- Published location reference
- Breaking Ground on Meta’s First Data Center in Canada · Meta
- Heartland Activity Update · Sturgeon County
- Greenlight Electricity Centre final investment decision, 2 July 2026 · Pembina Pipeline filing on SEC EDGAR
- Capital Power Enters Long-term Energy Supply Agreement with · Issuer press release via GlobeNewswire
Lifecycle
Under constructionMeta announced groundbreaking in July 2026. The county’s August update distinguishes site preparation from remaining building and safety permits.
- Evidence date
- 2026-08
- Checked
- 2026-10-05
- Scope
- Facility
- Evidence type
- Reported
- Status describes
- Facility or project lifecycle
- Breaking Ground on Meta’s First Data Center in Canada · Meta
- Heartland Activity Update · Sturgeon County
- Greenlight Electricity Centre final investment decision, 2 July 2026 · Pembina Pipeline filing on SEC EDGAR
- Capital Power Enters Long-term Energy Supply Agreement with · Issuer press release via GlobeNewswire
Capacity
PlannedMeta markets a 1 GW AI-focused data centre. The announcement does not define this as net server IT load.
- Evidence date
- 2026-07
- Checked
- 2026-10-05
- Scope
- Facility
- Evidence type
- Reported
- Status describes
- Capacity at stated basis and scope
- Quantity type
- Campus total
- Basis
- proposed
- Reported quantity
- 1000 MW
- Breaking Ground on Meta’s First Data Center in Canada · Meta
- Heartland Activity Update · Sturgeon County
- Greenlight Electricity Centre final investment decision, 2 July 2026 · Pembina Pipeline filing on SEC EDGAR
- Capital Power Enters Long-term Energy Supply Agreement with · Issuer press release via GlobeNewswire
Capacity
ApprovedThe county reports a 970 MW grid-connection approval. This is a connection quantity, not commissioned IT demand.
- Evidence date
- 2026-08
- Checked
- 2026-10-05
- Scope
- Facility
- Evidence type
- Reported
- Status describes
- Capacity at stated basis and scope
- Quantity type
- Utility supply
- Basis
- approved
- Reported quantity
- 970 MW
- Breaking Ground on Meta’s First Data Center in Canada · Meta
- Heartland Activity Update · Sturgeon County
- Greenlight Electricity Centre final investment decision, 2 July 2026 · Pembina Pipeline filing on SEC EDGAR
- Capital Power Enters Long-term Energy Supply Agreement with · Issuer press release via GlobeNewswire
Capacity
PlannedGreenlight’s dedicated supply project is a separate 932 MW gas-fired generating plant targeting the second half of 2030; it is not additional data-centre IT capacity.
- Evidence date
- 2026-07-02
- Checked
- 2026-10-05
- Scope
- Associated power plant · Greenlight initial plant
- Evidence type
- Reported
- Status describes
- Capacity at stated basis and scope
- Quantity type
- Generation
- Basis
- contracted
- Reported quantity
- 932 MW
- Breaking Ground on Meta’s First Data Center in Canada · Meta
- Heartland Activity Update · Sturgeon County
- Greenlight Electricity Centre final investment decision, 2 July 2026 · Pembina Pipeline filing on SEC EDGAR
- Capital Power Enters Long-term Energy Supply Agreement with · Issuer press release via GlobeNewswire
Power
PlannedThe supply plan includes dedicated gas generation and grid arrangements. Meta’s clean/renewable matching commitment is contractual accounting, not evidence that all physical electricity is gas-free.
- Evidence date
- Undated source
- Checked
- 2026-10-05
- Scope
- Facility
- Evidence type
- Reported
- Status describes
- Power supply or backup configuration
- Breaking Ground on Meta’s First Data Center in Canada · Meta
- Heartland Activity Update · Sturgeon County
- Greenlight Electricity Centre final investment decision, 2 July 2026 · Pembina Pipeline filing on SEC EDGAR
- Capital Power Enters Long-term Energy Supply Agreement with · Issuer press release via GlobeNewswire
Cooling
PlannedMeta plans recirculating liquid cooling with dry heat rejection and no routine water consumption by the cooling system; commissioning has not been established.
- Evidence date
- 2026-07
- Checked
- 2026-10-05
- Scope
- Facility
- Evidence type
- Reported
- Status describes
- Cooling system at stated scope
- Breaking Ground on Meta’s First Data Center in Canada · Meta
- Heartland Activity Update · Sturgeon County
- Greenlight Electricity Centre final investment decision, 2 July 2026 · Pembina Pipeline filing on SEC EDGAR
- Capital Power Enters Long-term Energy Supply Agreement with · Issuer press release via GlobeNewswire
Capacity
ContractedCapital Power announced a greater-than-ten-year agreement for 250 MW of capacity and energy supporting Meta’s site, with a target start in the second half of 2028. It is fleet-backed supply, not another site-capacity increment.
- Evidence date
- 2026-07-08
- Checked
- 2026-10-05
- Scope
- Facility
- Evidence type
- Reported
- Status describes
- Capacity at stated basis and scope
- Quantity type
- Utility supply
- Basis
- contracted
- Reported quantity
- 250 MW · Separate source-reported quantities are not additive.
- Breaking Ground on Meta’s First Data Center in Canada · Meta
- Heartland Activity Update · Sturgeon County
- Greenlight Electricity Centre final investment decision, 2 July 2026 · Pembina Pipeline filing on SEC EDGAR
- Capital Power Enters Long-term Energy Supply Agreement with · Issuer press release via GlobeNewswire
Commercial
ContractedGreenlight’s announcement names Siemens equipment and an Aecon/Técnicas Reunidas construction arrangement for the associated power plant.
- Evidence date
- 2026-07-02
- Checked
- 2026-10-05
- Scope
- Associated power plant
- Evidence type
- Reported
- Status describes
- Commercial disclosure or relationship
- Breaking Ground on Meta’s First Data Center in Canada · Meta
- Heartland Activity Update · Sturgeon County
- Greenlight Electricity Centre final investment decision, 2 July 2026 · Pembina Pipeline filing on SEC EDGAR
- Capital Power Enters Long-term Energy Supply Agreement with · Issuer press release via GlobeNewswire
Ownership
ReportedThe reviewed source identifies Meta in the operator or development role. This does not establish title to the underlying land.
- Evidence date
- Undated source
- Checked
- 2026-10-05
- Scope
- Facility
- Evidence type
- Reported
- Status describes
- Ownership operator or developer relationship
- Breaking Ground on Meta’s First Data Center in Canada · Meta
- Heartland Activity Update · Sturgeon County
- Greenlight Electricity Centre final investment decision, 2 July 2026 · Pembina Pipeline filing on SEC EDGAR
- Capital Power Enters Long-term Energy Supply Agreement with · Issuer press release via GlobeNewswire