Version-specific research record
WhiteFiber / Enovum MTL-3
WhiteFiber / Enovum Data Centers · Saint-Jérôme, Quebec
Record QC-WHITEFIBER-MTL3 · 2026-10-06-83c11c799ab4-public-2026-10-07
Current selected data edition. Evidence reviewed through 2026-10-06. Edition publication date: 2026-10-07.
Research record, not a building count. Campus and phase overlap may exist; do not add capacity values.
Current record profile · This edition’s record JSON · Edition overview
Identity provenance
- name: WhiteFiber, Inc.
- operator: WhiteFiber, Inc.
- province: WhiteFiber, Inc.
- city: WhiteFiber, Inc.
- record_kind: WhiteFiber, Inc.
- disposition: WhiteFiber, Inc.
Lifecycle
The August 2026 filing states that MTL-3 became operational in November 2025; WhiteFiber acquired the Saint-Jérôme property in May 2026.
- Evidence date
- 2026-08-12
- Checked
- 2026-10-05
- Scope
- Facility
- Evidence type
- Reported
- Status describes
- Facility or project lifecycle
- wyfi-20260630 · WhiteFiber, Inc.
Permanent claim link · Claim pub-quebec-east-QC-WHITEFIBER-MTL3-1
Citation text (select to copy)
Clarion Solutions. WhiteFiber / Enovum MTL-3. Canadian Data Centre Atlas. Record QC-WHITEFIBER-MTL3; claim pub-quebec-east-QC-WHITEFIBER-MTL3-1. Edition 2026-10-06-83c11c799ab4-public-2026-10-07 (publication date: 2026-10-07); evidence review through 2026-10-06. Claim evidence date: 2026-08-12; source checked: 2026-10-05. https://data.clarionsolutions.ca/canada-data-centres/editions/2026-10-06-83c11c799ab4-public-2026-10-07/records/QC-WHITEFIBER-MTL3/#claim-pub-quebec-east-QC-WHITEFIBER-MTL3-1
Cite the linked primary evidence as well. Publication and access dates do not establish current operations.
Capacity
ReportedThe filing describes MTL-3 as 7 MW gross.
- Evidence date
- 2026-08-12
- Checked
- 2026-10-05
- Scope
- Facility
- Evidence type
- Reported
- Status describes
- Reported capacity
- Quantity type
- Facility power
- Basis
- gross facility rating; not equivalent to IT load or measured demand
- Reported quantity
- 7 MW
- wyfi-20260630 · WhiteFiber, Inc.
Permanent claim link · Claim pub-quebec-east-QC-WHITEFIBER-MTL3-2
Citation text (select to copy)
Clarion Solutions. WhiteFiber / Enovum MTL-3. Canadian Data Centre Atlas. Record QC-WHITEFIBER-MTL3; claim pub-quebec-east-QC-WHITEFIBER-MTL3-2. Edition 2026-10-06-83c11c799ab4-public-2026-10-07 (publication date: 2026-10-07); evidence review through 2026-10-06. Claim evidence date: 2026-08-12; source checked: 2026-10-05. https://data.clarionsolutions.ca/canada-data-centres/editions/2026-10-06-83c11c799ab4-public-2026-10-07/records/QC-WHITEFIBER-MTL3/#claim-pub-quebec-east-QC-WHITEFIBER-MTL3-2
Cite the linked primary evidence as well. Publication and access dates do not establish current operations.
Capacity
ReportedMTL-3’s Cerebras contract is for 5 MW IT load, within its 7 MW gross design.
- Evidence date
- 2026-08-12
- Checked
- 2026-10-05
- Scope
- Facility
- Evidence type
- Reported
- Status describes
- Reported capacity
- Quantity type
- It load
- Basis
- tenant-contracted IT capacity, not incremental to gross facility power
- Reported quantity
- 5 MW
- wyfi-20260630 · WhiteFiber, Inc.
Permanent claim link · Claim pub-quebec-east-QC-WHITEFIBER-MTL3-3
Citation text (select to copy)
Clarion Solutions. WhiteFiber / Enovum MTL-3. Canadian Data Centre Atlas. Record QC-WHITEFIBER-MTL3; claim pub-quebec-east-QC-WHITEFIBER-MTL3-3. Edition 2026-10-06-83c11c799ab4-public-2026-10-07 (publication date: 2026-10-07); evidence review through 2026-10-06. Claim evidence date: 2026-08-12; source checked: 2026-10-05. https://data.clarionsolutions.ca/canada-data-centres/editions/2026-10-06-83c11c799ab4-public-2026-10-07/records/QC-WHITEFIBER-MTL3/#claim-pub-quebec-east-QC-WHITEFIBER-MTL3-3
Cite the linked primary evidence as well. Publication and access dates do not establish current operations.
Cooling
ReportedWhiteFiber’s MTL-3 page describes direct-to-chip liquid cooling, N+1 systems and carrier-neutral connectivity; exact physical route diversity is not independently established.
- Evidence date
- Undated source
- Checked
- 2026-10-05
- Scope
- Facility
- Evidence type
- Reported
- Status describes
- Cooling configuration
- MTL-3 | WhiteFiber · WhiteFiber
Permanent claim link · Claim pub-quebec-east-QC-WHITEFIBER-MTL3-4
Citation text (select to copy)
Clarion Solutions. WhiteFiber / Enovum MTL-3. Canadian Data Centre Atlas. Record QC-WHITEFIBER-MTL3; claim pub-quebec-east-QC-WHITEFIBER-MTL3-4. Edition 2026-10-06-83c11c799ab4-public-2026-10-07 (publication date: 2026-10-07); evidence review through 2026-10-06. Claim evidence date: undated; source checked: 2026-10-05. https://data.clarionsolutions.ca/canada-data-centres/editions/2026-10-06-83c11c799ab4-public-2026-10-07/records/QC-WHITEFIBER-MTL3/#claim-pub-quebec-east-QC-WHITEFIBER-MTL3-4
Cite the linked primary evidence as well. Publication and access dates do not establish current operations.
Commercial
ReportedThe filing states Cerebras billing began November 1, 2025 at C$1.4 million monthly under a five-year contract; this is tenant-specific, not market pricing.
- Evidence date
- 2026-08-12
- Checked
- 2026-10-05
- Scope
- Facility
- Evidence type
- Reported
- Status describes
- Commercial disclosure
- wyfi-20260630 · WhiteFiber, Inc.
Permanent claim link · Claim pub-quebec-east-QC-WHITEFIBER-MTL3-5
Citation text (select to copy)
Clarion Solutions. WhiteFiber / Enovum MTL-3. Canadian Data Centre Atlas. Record QC-WHITEFIBER-MTL3; claim pub-quebec-east-QC-WHITEFIBER-MTL3-5. Edition 2026-10-06-83c11c799ab4-public-2026-10-07 (publication date: 2026-10-07); evidence review through 2026-10-06. Claim evidence date: 2026-08-12; source checked: 2026-10-05. https://data.clarionsolutions.ca/canada-data-centres/editions/2026-10-06-83c11c799ab4-public-2026-10-07/records/QC-WHITEFIBER-MTL3/#claim-pub-quebec-east-QC-WHITEFIBER-MTL3-5
Cite the linked primary evidence as well. Publication and access dates do not establish current operations.