BUZZ HPC 320 MW AI gigafactory
BUZZ High Performance Computing / HIVE · Greater Toronto Area, Ontario
Record on-113 · 2026-10-06-83c11c799ab4-public-2026-10-06
Historical published edition. Do not treat these as newer or additional facts. Evidence reviewed through 2026-10-06. Edition publication date: 2026-10-06.
Research record, not a building count. Campus and phase overlap may exist; do not add capacity values.
Current record profile · This edition’s record JSON · Edition overview
Identity provenance
- city: HIVE Digital Technologies, via SEC
- disposition: HIVE Digital Technologies, via SEC
- name: HIVE Digital Technologies, via SEC
- operator: HIVE Digital Technologies, via SEC
- province: HIVE Digital Technologies, via SEC
- record_kind: HIVE Digital Technologies, via SEC
Lifecycle
PlannedHIVE’s May 2026 announcement targets second-half 2027 for the planned Greater Toronto Area AI campus.
- Evidence date
- 2026-05-18
- Checked
- 2026-10-05
- Scope
- Facility
- Evidence type
- Reported
- Status describes
- Facility or project lifecycle
- HIVE/BUZZ 320 MW GTA project announcement, SEC exhibit · HIVE Digital Technologies, via SEC
Permanent claim link · Claim pub-ontario_a-on-113-1
Citation text (select to copy)
Clarion Solutions. BUZZ HPC 320 MW AI gigafactory. Canadian Data Centre Atlas. Record on-113; claim pub-ontario_a-on-113-1. Edition 2026-10-06-83c11c799ab4-public-2026-10-06 (publication date: 2026-10-06); evidence review through 2026-10-06. Claim evidence date: 2026-05-18; source checked: 2026-10-05. https://data.clarionsolutions.ca/canada-data-centres/editions/2026-10-06-83c11c799ab4-public-2026-10-06/records/on-113/#claim-pub-ontario_a-on-113-1
Cite the linked primary evidence as well. Publication and access dates do not establish current operations.
Capacity
PlannedThe issuer reports a 320 MW utility-power allocation for the acquired site. The filing does not provide an executed utility agreement or establish energized IT capacity.
- Evidence date
- 2026-05-18
- Checked
- 2026-10-05
- Scope
- Campus
- Evidence type
- Reported
- Status describes
- Capacity at stated basis and scope
- Quantity type
- Utility
- Basis
- issuer-reported allocation; unverified energization
- Reported quantity
- 320 MW
- HIVE/BUZZ 320 MW GTA project announcement, SEC exhibit · HIVE Digital Technologies, via SEC
Permanent claim link · Claim pub-ontario_a-on-113-2
Citation text (select to copy)
Clarion Solutions. BUZZ HPC 320 MW AI gigafactory. Canadian Data Centre Atlas. Record on-113; claim pub-ontario_a-on-113-2. Edition 2026-10-06-83c11c799ab4-public-2026-10-06 (publication date: 2026-10-06); evidence review through 2026-10-06. Claim evidence date: 2026-05-18; source checked: 2026-10-05. https://data.clarionsolutions.ca/canada-data-centres/editions/2026-10-06-83c11c799ab4-public-2026-10-06/records/on-113/#claim-pub-ontario_a-on-113-2
Cite the linked primary evidence as well. Publication and access dates do not establish current operations.
Cooling
PlannedThe design calls for Ontario-grid electricity and closed-loop cooling with a no-water-use approach; these are project intentions, not installed-system evidence.
- Evidence date
- 2026-05-18
- Checked
- 2026-10-05
- Scope
- Facility
- Evidence type
- Reported
- Status describes
- Power supply or backup configuration
- HIVE/BUZZ 320 MW GTA project announcement, SEC exhibit · HIVE Digital Technologies, via SEC
Permanent claim link · Claim pub-ontario_a-on-113-3
Citation text (select to copy)
Clarion Solutions. BUZZ HPC 320 MW AI gigafactory. Canadian Data Centre Atlas. Record on-113; claim pub-ontario_a-on-113-3. Edition 2026-10-06-83c11c799ab4-public-2026-10-06 (publication date: 2026-10-06); evidence review through 2026-10-06. Claim evidence date: 2026-05-18; source checked: 2026-10-05. https://data.clarionsolutions.ca/canada-data-centres/editions/2026-10-06-83c11c799ab4-public-2026-10-06/records/on-113/#claim-pub-ontario_a-on-113-3
Cite the linked primary evidence as well. Publication and access dates do not establish current operations.
Hardware
PlannedThe full-buildout design targets more than 100,000 GPUs; models, procurement and installed inventory are not established.
- Evidence date
- 2026-05-18
- Checked
- 2026-10-05
- Scope
- Campus
- Evidence type
- Reported
- Status describes
- Hardware deployment procurement or support
- HIVE/BUZZ 320 MW GTA project announcement, SEC exhibit · HIVE Digital Technologies, via SEC
Permanent claim link · Claim pub-ontario_a-on-113-4
Citation text (select to copy)
Clarion Solutions. BUZZ HPC 320 MW AI gigafactory. Canadian Data Centre Atlas. Record on-113; claim pub-ontario_a-on-113-4. Edition 2026-10-06-83c11c799ab4-public-2026-10-06 (publication date: 2026-10-06); evidence review through 2026-10-06. Claim evidence date: 2026-05-18; source checked: 2026-10-05. https://data.clarionsolutions.ca/canada-data-centres/editions/2026-10-06-83c11c799ab4-public-2026-10-06/records/on-113/#claim-pub-ontario_a-on-113-4
Cite the linked primary evidence as well. Publication and access dates do not establish current operations.
Ownership
ReportedHIVE states that its BUZZ subsidiary acquired adjoining parcels of approximately 21 and 4 acres.
- Evidence date
- 2026-05-18
- Checked
- 2026-10-05
- Scope
- Facility
- Evidence type
- Reported
- Status describes
- Ownership operator or developer relationship
- HIVE/BUZZ 320 MW GTA project announcement, SEC exhibit · HIVE Digital Technologies, via SEC
Permanent claim link · Claim pub-ontario_a-on-113-5
Citation text (select to copy)
Clarion Solutions. BUZZ HPC 320 MW AI gigafactory. Canadian Data Centre Atlas. Record on-113; claim pub-ontario_a-on-113-5. Edition 2026-10-06-83c11c799ab4-public-2026-10-06 (publication date: 2026-10-06); evidence review through 2026-10-06. Claim evidence date: 2026-05-18; source checked: 2026-10-05. https://data.clarionsolutions.ca/canada-data-centres/editions/2026-10-06-83c11c799ab4-public-2026-10-06/records/on-113/#claim-pub-ontario_a-on-113-5
Cite the linked primary evidence as well. Publication and access dates do not establish current operations.