CLARION Data projects

Version-specific research record

Cologix TOR3

Cologix · Toronto, Ontario

Record on-012 · 2026-10-06-83c11c799ab4-public-2026-10-06

Historical published edition. Do not treat these as newer or additional facts. Evidence reviewed through 2026-10-06. Edition publication date: 2026-10-06.

Research record, not a building count. Campus and phase overlap may exist; do not add capacity values.

Current record profile · This edition’s record JSON · Edition overview

Identity provenance

Location

Reported

905 King Street West, Toronto, Ontario; TOR3 is described as an expansion on the TOR2 campus.

Evidence date
Undated source
Checked
2026-10-05
Scope
Facility
Evidence type
Reported
Status describes
Published location reference
Citation text (select to copy)

Clarion Solutions. Cologix TOR3. Canadian Data Centre Atlas. Record on-012; claim pub-expand-on-012-public_location. Edition 2026-10-06-83c11c799ab4-public-2026-10-06 (publication date: 2026-10-06); evidence review through 2026-10-06. Claim evidence date: undated; source checked: 2026-10-05. https://data.clarionsolutions.ca/canada-data-centres/editions/2026-10-06-83c11c799ab4-public-2026-10-06/records/on-012/#claim-pub-expand-on-012-public_location

Cite the linked primary evidence as well. Publication and access dates do not establish current operations.

Capacity

Reported

Cologix advertises 2 MW with A/B distribution for TOR3; this is not labelled measured IT load.

Evidence date
Undated source
Checked
2026-10-05
Scope
Facility
Evidence type
Reported
Status describes
Capacity assertion
Quantity type
Unspecified power
Basis
TOR3 expansion power with A/B distribution; IT-versus-utility basis unspecified
Reported quantity
2 MW
Citation text (select to copy)

Clarion Solutions. Cologix TOR3. Canadian Data Centre Atlas. Record on-012; claim pub-expand-on-012-advertised_power. Edition 2026-10-06-83c11c799ab4-public-2026-10-06 (publication date: 2026-10-06); evidence review through 2026-10-06. Claim evidence date: undated; source checked: 2026-10-05. https://data.clarionsolutions.ca/canada-data-centres/editions/2026-10-06-83c11c799ab4-public-2026-10-06/records/on-012/#claim-pub-expand-on-012-advertised_power

Cite the linked primary evidence as well. Publication and access dates do not establish current operations.

Cooling

Reported

Cologix lists N+1 chillers and cooling towers, plus in-row cooling with hot-aisle containment.

Evidence date
Undated source
Checked
2026-10-05
Scope
Facility
Evidence type
Reported
Status describes
Cooling configuration
Citation text (select to copy)

Clarion Solutions. Cologix TOR3. Canadian Data Centre Atlas. Record on-012; claim pub-expand-on-012-cooling_configuration. Edition 2026-10-06-83c11c799ab4-public-2026-10-06 (publication date: 2026-10-06); evidence review through 2026-10-06. Claim evidence date: undated; source checked: 2026-10-05. https://data.clarionsolutions.ca/canada-data-centres/editions/2026-10-06-83c11c799ab4-public-2026-10-06/records/on-012/#claim-pub-expand-on-012-cooling_configuration