CLARION Data projects

Browse this record in the Atlas

Facility · Evidence reviewed 2026-10-06

Chip WAT1

CHIP Data Centers · Waterloo, Ontario

Research record, not a building count. Campus and phase overlap may exist; do not add capacity values. Access dates do not establish fresh commissioning.

Identity and map provenance

City reference only; not the facility. Derived city center, rounded to four decimals. The marker is not a building, entrance, campus or parcel location. GeoNames 6176823 · CC BY 4.0

Location

Reported

CHIP Data Centers identifies WAT1 in Waterloo, Ontario. No street address or parcel ownership is established.

Evidence date
Undated source
Checked
2026-10-05
Scope
Facility
Evidence type
Reported
Status describes
Operator marketed facility identity

Power

Marketed

The marketed design combines grid supply, N+1 UPS and diesel backup, with 48-hour backup runtime.

Evidence date
Undated source
Checked
2026-10-05
Scope
Facility
Evidence type
Reported
Status describes
Power supply or backup configuration

Cooling

Marketed

CHIP advertises air and liquid-to-chip cooling for racks up to 200 kW; installed scope is not independently established.

Evidence date
Undated source
Checked
2026-10-05
Scope
Facility
Evidence type
Reported
Status describes
Cooling system at stated scope

Hardware

Supported

NVIDIA B300 and GB300 NVL72 are listed as supported hardware, not an installed or purchased fleet.

Evidence date
Undated source
Checked
2026-10-05
Scope
Facility
Evidence type
Reported
Status describes
Hardware deployment procurement or support

Capacity

Marketed

WAT1 markets 4 MW ready-for-service in 2026; its detailed table separates 2 MW primary power and 2 MW expansion. These are operator schedules, not verified energized IT load.

Evidence date
Undated source
Checked
2026-10-05
Scope
Facility
Evidence type
Reported
Status describes
Facility or project lifecycle
Quantity type
Unspecified power
Basis
marketed 2026 RFS total
Reported quantity
4 MW

Capacity

Planned

The operator targets 8 MW total in 2027.

Evidence date
Undated source
Checked
2026-10-05
Scope
Facility
Evidence type
Reported
Status describes
Capacity at stated basis and scope
Quantity type
Unspecified power
Basis
2027 target
Reported quantity
8 MW