Centrilogic Mississauga North

Centrilogic · Mississauga, Ontario

Record on-042 · 2026-10-06-83c11c799ab4-public-2026-10-07

Current selected data edition. Evidence reviewed through 2026-10-06. Edition publication date: 2026-10-07.

Research record, not a building count. Campus and phase overlap may exist; do not add capacity values.

Current record profile · This edition’s record JSON · Edition overview

Identity provenance

Location

Reported

Centrilogic markets its Mississauga North data centre in Mississauga, Ontario. The page establishes an offering, not a new commissioning date.

Evidence date
Undated source
Checked
2026-10-05
Scope
Facility
Evidence type
Reported
Status describes
Operator marketed facility identity
Citation text (select to copy)

Clarion Solutions. Centrilogic Mississauga North. Canadian Data Centre Atlas. Record on-042; claim pub-ontario_a-on-042-1. Edition 2026-10-06-83c11c799ab4-public-2026-10-07 (publication date: 2026-10-07); evidence review through 2026-10-06. Claim evidence date: undated; source checked: 2026-10-05. https://data.clarionsolutions.ca/canada-data-centres/editions/2026-10-06-83c11c799ab4-public-2026-10-07/records/on-042/#claim-pub-ontario_a-on-042-1

Cite the linked primary evidence as well. Publication and access dates do not establish current operations.

Power

Installed

The operator lists A/B distribution, N+1 UPS and a Caterpillar diesel generator with 48 hours of standby fuel and hot filling.

Evidence date
Undated source
Checked
2026-10-05
Scope
Facility
Evidence type
Reported
Status describes
Power supply or backup configuration
Citation text (select to copy)

Clarion Solutions. Centrilogic Mississauga North. Canadian Data Centre Atlas. Record on-042; claim pub-ontario_a-on-042-2. Edition 2026-10-06-83c11c799ab4-public-2026-10-07 (publication date: 2026-10-07); evidence review through 2026-10-06. Claim evidence date: undated; source checked: 2026-10-05. https://data.clarionsolutions.ca/canada-data-centres/editions/2026-10-06-83c11c799ab4-public-2026-10-07/records/on-042/#claim-pub-ontario_a-on-042-2

Cite the linked primary evidence as well. Publication and access dates do not establish current operations.

Cooling

Installed

The specification describes N+N independent cooling units and hot/cold aisles.

Evidence date
Undated source
Checked
2026-10-05
Scope
Facility
Evidence type
Reported
Status describes
Cooling system at stated scope
Citation text (select to copy)

Clarion Solutions. Centrilogic Mississauga North. Canadian Data Centre Atlas. Record on-042; claim pub-ontario_a-on-042-3. Edition 2026-10-06-83c11c799ab4-public-2026-10-07 (publication date: 2026-10-07); evidence review through 2026-10-06. Claim evidence date: undated; source checked: 2026-10-05. https://data.clarionsolutions.ca/canada-data-centres/editions/2026-10-06-83c11c799ab4-public-2026-10-07/records/on-042/#claim-pub-ontario_a-on-042-3

Cite the linked primary evidence as well. Publication and access dates do not establish current operations.

Connectivity

Installed

The page describes multiple backbone providers, redundant building fibre connections and inter-facility links; it does not establish a fully diverse end-to-end route map.

Evidence date
Undated source
Checked
2026-10-05
Scope
Facility
Evidence type
Reported
Status describes
Connectivity infrastructure or service
Citation text (select to copy)

Clarion Solutions. Centrilogic Mississauga North. Canadian Data Centre Atlas. Record on-042; claim pub-ontario_a-on-042-4. Edition 2026-10-06-83c11c799ab4-public-2026-10-07 (publication date: 2026-10-07); evidence review through 2026-10-06. Claim evidence date: undated; source checked: 2026-10-05. https://data.clarionsolutions.ca/canada-data-centres/editions/2026-10-06-83c11c799ab4-public-2026-10-07/records/on-042/#claim-pub-ontario_a-on-042-4

Cite the linked primary evidence as well. Publication and access dates do not establish current operations.