Version-specific research record
Urbacon Toronto DC5
Urbacon Data Centre Solutions · Richmond Hill, Ontario
Record on-034 · 2026-10-06-83c11c799ab4-public-2026-10-07
Current selected data edition. Evidence reviewed through 2026-10-06. Edition publication date: 2026-10-07.
Research record, not a building count. Campus and phase overlap may exist; do not add capacity values.
Current record profile · This edition’s record JSON · Edition overview
Identity provenance
- name: Urbacon Data Centre Solutions
- operator: Urbacon Data Centre Solutions
- province: Urbacon Data Centre Solutions
- city: Urbacon Data Centre Solutions
- record_kind: Urbacon Data Centre Solutions
- disposition: Urbacon Data Centre Solutions
Location
ReportedUDCS locates DC5 at Barker Business Park in Richmond Hill, Ontario; no street number is assigned.
- Evidence date
- Undated source
- Checked
- 2026-10-05
- Scope
- Facility
- Evidence type
- Reported
- Status describes
- Published location reference
- DC5 - Urbacon Data Centre Solutions · Urbacon Data Centre Solutions
Permanent claim link · Claim pub-ontario_b-on-034-location
Citation text (select to copy)
Clarion Solutions. Urbacon Toronto DC5. Canadian Data Centre Atlas. Record on-034; claim pub-ontario_b-on-034-location. Edition 2026-10-06-83c11c799ab4-public-2026-10-07 (publication date: 2026-10-07); evidence review through 2026-10-06. Claim evidence date: undated; source checked: 2026-10-05. https://data.clarionsolutions.ca/canada-data-centres/editions/2026-10-06-83c11c799ab4-public-2026-10-07/records/on-034/#claim-pub-ontario_b-on-034-location
Cite the linked primary evidence as well. Publication and access dates do not establish current operations.
Lifecycle
In developmentUDCS’s undated available-sites page describes DC5 as in development.
- Evidence date
- Undated source
- Checked
- 2026-10-05
- Scope
- Facility
- Evidence type
- Reported
- Status describes
- Facility or project lifecycle
- Available Sites - Urbacon Data Centre Solutions · Urbacon Data Centre Solutions
Permanent claim link · Claim pub-ontario_b-on-034-project_status
Citation text (select to copy)
Clarion Solutions. Urbacon Toronto DC5. Canadian Data Centre Atlas. Record on-034; claim pub-ontario_b-on-034-project_status. Edition 2026-10-06-83c11c799ab4-public-2026-10-07 (publication date: 2026-10-07); evidence review through 2026-10-06. Claim evidence date: undated; source checked: 2026-10-05. https://data.clarionsolutions.ca/canada-data-centres/editions/2026-10-06-83c11c799ab4-public-2026-10-07/records/on-034/#claim-pub-ontario_b-on-034-project_status
Cite the linked primary evidence as well. Publication and access dates do not establish current operations.
Capacity
PlannedUDCS advertises up to 65 MW of critical IT/design power for DC5, not commissioned IT capacity.
- Evidence date
- Undated source
- Checked
- 2026-10-05
- Scope
- Facility
- Evidence type
- Reported
- Status describes
- Capacity at stated basis and scope
- Quantity type
- It design capacity
- Basis
- operator-advertised design/planned critical IT capacity
- Reported quantity
- 65 MW · up_to
- Toronto, Canada - Urbacon Data Centre Solutions · Urbacon Data Centre Solutions
- DC5 - Urbacon Data Centre Solutions · Urbacon Data Centre Solutions
Permanent claim link · Claim pub-ontario_b-on-034-critical_design
Citation text (select to copy)
Clarion Solutions. Urbacon Toronto DC5. Canadian Data Centre Atlas. Record on-034; claim pub-ontario_b-on-034-critical_design. Edition 2026-10-06-83c11c799ab4-public-2026-10-07 (publication date: 2026-10-07); evidence review through 2026-10-06. Claim evidence date: undated; source checked: 2026-10-05. https://data.clarionsolutions.ca/canada-data-centres/editions/2026-10-06-83c11c799ab4-public-2026-10-07/records/on-034/#claim-pub-ontario_b-on-034-critical_design
Cite the linked primary evidence as well. Publication and access dates do not establish current operations.
Capacity
ReportedUDCS says 80 MW of total power is secured for DC5. This is not an independently verified utility commitment or usable-IT figure.
- Evidence date
- Undated source
- Checked
- 2026-10-05
- Scope
- Facility
- Evidence type
- Reported
- Status describes
- Capacity at stated basis and scope
- Quantity type
- Utility supply
- Basis
- operator-reported total power secured
- Reported quantity
- 80 MW
- Available Sites - Urbacon Data Centre Solutions · Urbacon Data Centre Solutions
Permanent claim link · Claim pub-ontario_b-on-034-secured_power_claim
Citation text (select to copy)
Clarion Solutions. Urbacon Toronto DC5. Canadian Data Centre Atlas. Record on-034; claim pub-ontario_b-on-034-secured_power_claim. Edition 2026-10-06-83c11c799ab4-public-2026-10-07 (publication date: 2026-10-07); evidence review through 2026-10-06. Claim evidence date: undated; source checked: 2026-10-05. https://data.clarionsolutions.ca/canada-data-centres/editions/2026-10-06-83c11c799ab4-public-2026-10-07/records/on-034/#claim-pub-ontario_b-on-034-secured_power_claim
Cite the linked primary evidence as well. Publication and access dates do not establish current operations.
Cooling
PlannedUDCS advertises free-air, liquid-cooled and hybrid design options; the final commissioned cooling system is not established.
- Evidence date
- Undated source
- Checked
- 2026-10-05
- Scope
- Facility
- Evidence type
- Reported
- Status describes
- Cooling system at stated scope
- Available Sites - Urbacon Data Centre Solutions · Urbacon Data Centre Solutions
Permanent claim link · Claim pub-ontario_b-on-034-cooling_options
Citation text (select to copy)
Clarion Solutions. Urbacon Toronto DC5. Canadian Data Centre Atlas. Record on-034; claim pub-ontario_b-on-034-cooling_options. Edition 2026-10-06-83c11c799ab4-public-2026-10-07 (publication date: 2026-10-07); evidence review through 2026-10-06. Claim evidence date: undated; source checked: 2026-10-05. https://data.clarionsolutions.ca/canada-data-centres/editions/2026-10-06-83c11c799ab4-public-2026-10-07/records/on-034/#claim-pub-ontario_b-on-034-cooling_options
Cite the linked primary evidence as well. Publication and access dates do not establish current operations.
Ownership
ReportedUrbacon Data Centre Solutions markets and develops the project; the legal titleholding entity is not named.
- Evidence date
- Undated source
- Checked
- 2026-10-05
- Scope
- Facility
- Evidence type
- Reported
- Status describes
- Ownership operator or developer relationship
- DC5 - Urbacon Data Centre Solutions · Urbacon Data Centre Solutions
Permanent claim link · Claim pub-ontario_b-on-034-developer
Citation text (select to copy)
Clarion Solutions. Urbacon Toronto DC5. Canadian Data Centre Atlas. Record on-034; claim pub-ontario_b-on-034-developer. Edition 2026-10-06-83c11c799ab4-public-2026-10-07 (publication date: 2026-10-07); evidence review through 2026-10-06. Claim evidence date: undated; source checked: 2026-10-05. https://data.clarionsolutions.ca/canada-data-centres/editions/2026-10-06-83c11c799ab4-public-2026-10-07/records/on-034/#claim-pub-ontario_b-on-034-developer
Cite the linked primary evidence as well. Publication and access dates do not establish current operations.
Power readiness
ReportedUDCS reports zoning approval and power secured for DC5; the page does not state energization or IT commissioning.
- Evidence date
- Undated source
- Checked
- 2026-10-05
- Scope
- Facility
- Evidence type
- Reported
- Status describes
- Power milestone at stated scope
- Toronto, Canada - Urbacon Data Centre Solutions · Urbacon Data Centre Solutions
- Available Sites - Urbacon Data Centre Solutions · Urbacon Data Centre Solutions
Permanent claim link · Claim pub-ontario_b-on-034-readiness
Citation text (select to copy)
Clarion Solutions. Urbacon Toronto DC5. Canadian Data Centre Atlas. Record on-034; claim pub-ontario_b-on-034-readiness. Edition 2026-10-06-83c11c799ab4-public-2026-10-07 (publication date: 2026-10-07); evidence review through 2026-10-06. Claim evidence date: undated; source checked: 2026-10-05. https://data.clarionsolutions.ca/canada-data-centres/editions/2026-10-06-83c11c799ab4-public-2026-10-07/records/on-034/#claim-pub-ontario_b-on-034-readiness
Cite the linked primary evidence as well. Publication and access dates do not establish current operations.
Commercial
ReportedThe operator markets DC5 for lease; no specific executed customer lease or vacant MW is disclosed.
- Evidence date
- Undated source
- Checked
- 2026-10-05
- Scope
- Facility
- Evidence type
- Reported
- Status describes
- Marketed service
- DC5 - Urbacon Data Centre Solutions · Urbacon Data Centre Solutions
Permanent claim link · Claim pub-ontario_b-on-034-marketing
Citation text (select to copy)
Clarion Solutions. Urbacon Toronto DC5. Canadian Data Centre Atlas. Record on-034; claim pub-ontario_b-on-034-marketing. Edition 2026-10-06-83c11c799ab4-public-2026-10-07 (publication date: 2026-10-07); evidence review through 2026-10-06. Claim evidence date: undated; source checked: 2026-10-05. https://data.clarionsolutions.ca/canada-data-centres/editions/2026-10-06-83c11c799ab4-public-2026-10-07/records/on-034/#claim-pub-ontario_b-on-034-marketing
Cite the linked primary evidence as well. Publication and access dates do not establish current operations.