CLARION Data projects

Version-specific research record

Urbacon Toronto DC3

Urbacon Data Centre Solutions · Richmond Hill, Ontario

Record on-032 · 2026-10-06-83c11c799ab4-public-2026-10-07

Current selected data edition. Evidence reviewed through 2026-10-06. Edition publication date: 2026-10-07.

Research record, not a building count. Campus and phase overlap may exist; do not add capacity values.

Current record profile · This edition’s record JSON · Edition overview

Identity provenance

Location

Reported

UDCS identifies Toronto DC3 in Richmond Hill, Ontario; the street address is not confirmed by the retained source.

Evidence date
Undated source
Checked
2026-10-05
Scope
Facility
Evidence type
Reported
Status describes
Published location reference
Citation text (select to copy)

Clarion Solutions. Urbacon Toronto DC3. Canadian Data Centre Atlas. Record on-032; claim pub-ontario_b-on-032-location. Edition 2026-10-06-83c11c799ab4-public-2026-10-07 (publication date: 2026-10-07); evidence review through 2026-10-06. Claim evidence date: undated; source checked: 2026-10-05. https://data.clarionsolutions.ca/canada-data-centres/editions/2026-10-06-83c11c799ab4-public-2026-10-07/records/on-032/#claim-pub-ontario_b-on-032-location

Cite the linked primary evidence as well. Publication and access dates do not establish current operations.

Lifecycle

Historical completed

UDCS dates project completion to 2023-02. Present operation is separately described on its undated operating-facilities roster.

Evidence date
2023-02
Checked
2026-10-05
Scope
Facility
Evidence type
Reported
Status describes
Facility or project lifecycle
Citation text (select to copy)

Clarion Solutions. Urbacon Toronto DC3. Canadian Data Centre Atlas. Record on-032; claim pub-ontario_b-on-032-reported_status. Edition 2026-10-06-83c11c799ab4-public-2026-10-07 (publication date: 2026-10-07); evidence review through 2026-10-06. Claim evidence date: 2023-02; source checked: 2026-10-05. https://data.clarionsolutions.ca/canada-data-centres/editions/2026-10-06-83c11c799ab4-public-2026-10-07/records/on-032/#claim-pub-ontario_b-on-032-reported_status

Cite the linked primary evidence as well. Publication and access dates do not establish current operations.

Capacity

Reported

UDCS reports 18 MW of critical power for DC3. The figure is not current metered demand or verified vacant capacity.

Evidence date
Undated source
Checked
2026-10-05
Scope
Facility
Evidence type
Reported
Status describes
Capacity at stated basis and scope
Quantity type
Critical power
Basis
operator-reported facility critical-power rating
Reported quantity
18 MW
Citation text (select to copy)

Clarion Solutions. Urbacon Toronto DC3. Canadian Data Centre Atlas. Record on-032; claim pub-ontario_b-on-032-critical_power. Edition 2026-10-06-83c11c799ab4-public-2026-10-07 (publication date: 2026-10-07); evidence review through 2026-10-06. Claim evidence date: undated; source checked: 2026-10-05. https://data.clarionsolutions.ca/canada-data-centres/editions/2026-10-06-83c11c799ab4-public-2026-10-07/records/on-032/#claim-pub-ontario_b-on-032-critical_power

Cite the linked primary evidence as well. Publication and access dates do not establish current operations.

Ownership

Reported

UDCS identifies this facility within its developed and operated data-centre estate; registered title is not separately established.

Evidence date
Undated source
Checked
2026-10-05
Scope
Facility
Evidence type
Reported
Status describes
Ownership operator or developer relationship
Citation text (select to copy)

Clarion Solutions. Urbacon Toronto DC3. Canadian Data Centre Atlas. Record on-032; claim pub-ontario_b-on-032-operator. Edition 2026-10-06-83c11c799ab4-public-2026-10-07 (publication date: 2026-10-07); evidence review through 2026-10-06. Claim evidence date: undated; source checked: 2026-10-05. https://data.clarionsolutions.ca/canada-data-centres/editions/2026-10-06-83c11c799ab4-public-2026-10-07/records/on-032/#claim-pub-ontario_b-on-032-operator

Cite the linked primary evidence as well. Publication and access dates do not establish current operations.

Cooling

Reported

UDCS describes direct-evaporative cooling and rear-door heat exchangers in the DC3 project.

Evidence date
2023-02
Checked
2026-10-05
Scope
Facility
Evidence type
Reported
Status describes
Cooling system at stated scope
Citation text (select to copy)

Clarion Solutions. Urbacon Toronto DC3. Canadian Data Centre Atlas. Record on-032; claim pub-ontario_b-on-032-cooling. Edition 2026-10-06-83c11c799ab4-public-2026-10-07 (publication date: 2026-10-07); evidence review through 2026-10-06. Claim evidence date: 2023-02; source checked: 2026-10-05. https://data.clarionsolutions.ca/canada-data-centres/editions/2026-10-06-83c11c799ab4-public-2026-10-07/records/on-032/#claim-pub-ontario_b-on-032-cooling

Cite the linked primary evidence as well. Publication and access dates do not establish current operations.