Version-specific research record
TELUS / Westbank 150 West Georgia AI Factory
TELUS / Westbank · Vancouver, British Columbia
Record bc-telus-georgia150 · 2026-10-06-83c11c799ab4-public-2026-10-07
Current selected data edition. Evidence reviewed through 2026-10-06. Edition publication date: 2026-10-07.
Research record, not a building count. Campus and phase overlap may exist; do not add capacity values.
Current record profile · This edition’s record JSON · Edition overview
Identity provenance
- name: Issuer press release via CNW, Allied Properties REIT, City of Vancouver
- operator: Issuer press release via CNW, Allied Properties REIT, City of Vancouver
- province: Issuer press release via CNW, Allied Properties REIT, City of Vancouver
- city: Issuer press release via CNW, Allied Properties REIT, City of Vancouver
- record_kind: Issuer press release via CNW, Allied Properties REIT, City of Vancouver
- disposition: Issuer press release via CNW, Allied Properties REIT, City of Vancouver
Location
ReportedVancouver, British Columbia. City or regional reference only; no facility coordinates are published.
- Evidence date
- Undated source
- Checked
- 2026-10-05
- Scope
- Facility
- Evidence type
- Reported
- Status describes
- Published location reference
- TELUS and Government of Canada advance work to scale Canada's sovereign AI infrastructure · Issuer press release via CNW
- Allied Reports Q4 and Full-Year Results; Announces Leadership Update and Equity Financing · Allied Properties REIT
- CD-1 (818) - 720 Beatty Street and 701 Expo Boulevard · City of Vancouver
Permanent claim link · Claim pub-bc-telus-georgia150-review-1
Citation text (select to copy)
Clarion Solutions. TELUS / Westbank 150 West Georgia AI Factory. Canadian Data Centre Atlas. Record bc-telus-georgia150; claim pub-bc-telus-georgia150-review-1. Edition 2026-10-06-83c11c799ab4-public-2026-10-07 (publication date: 2026-10-07); evidence review through 2026-10-06. Claim evidence date: undated; source checked: 2026-10-05. https://data.clarionsolutions.ca/canada-data-centres/editions/2026-10-06-83c11c799ab4-public-2026-10-07/records/bc-telus-georgia150/#claim-pub-bc-telus-georgia150-review-1
Cite the linked primary evidence as well. Publication and access dates do not establish current operations.
Lifecycle
PlannedTELUS describes 150 West Georgia as part of a planned three-site BC AI cluster. The release’s target timetable is not confirmation of site permitting or operation.
- Evidence date
- Undated source
- Checked
- 2026-10-05
- Scope
- Facility
- Evidence type
- Reported
- Status describes
- Facility or project lifecycle
- TELUS and Government of Canada advance work to scale Canada's sovereign AI infrastructure · Issuer press release via CNW
- Allied Reports Q4 and Full-Year Results; Announces Leadership Update and Equity Financing · Allied Properties REIT
- CD-1 (818) - 720 Beatty Street and 701 Expo Boulevard · City of Vancouver
Permanent claim link · Claim pub-bc-telus-georgia150-review-2
Citation text (select to copy)
Clarion Solutions. TELUS / Westbank 150 West Georgia AI Factory. Canadian Data Centre Atlas. Record bc-telus-georgia150; claim pub-bc-telus-georgia150-review-2. Edition 2026-10-06-83c11c799ab4-public-2026-10-07 (publication date: 2026-10-07); evidence review through 2026-10-06. Claim evidence date: undated; source checked: 2026-10-05. https://data.clarionsolutions.ca/canada-data-centres/editions/2026-10-06-83c11c799ab4-public-2026-10-07/records/bc-telus-georgia150/#claim-pub-bc-telus-georgia150-review-2
Cite the linked primary evidence as well. Publication and access dates do not establish current operations.
Power
PlannedTELUS says it secured an initial 85 MW across three BC sites, with a cluster ambition above 150 MW by 2032. Neither total is assigned to this individual site.
- Evidence date
- Undated source
- Checked
- 2026-10-05
- Scope
- Three site cluster
- Evidence type
- Reported
- Status describes
- Power supply or backup configuration
- TELUS and Government of Canada advance work to scale Canada's sovereign AI infrastructure · Issuer press release via CNW
- Allied Reports Q4 and Full-Year Results; Announces Leadership Update and Equity Financing · Allied Properties REIT
- CD-1 (818) - 720 Beatty Street and 701 Expo Boulevard · City of Vancouver
Permanent claim link · Claim pub-bc-telus-georgia150-review-3
Citation text (select to copy)
Clarion Solutions. TELUS / Westbank 150 West Georgia AI Factory. Canadian Data Centre Atlas. Record bc-telus-georgia150; claim pub-bc-telus-georgia150-review-3. Edition 2026-10-06-83c11c799ab4-public-2026-10-07 (publication date: 2026-10-07); evidence review through 2026-10-06. Claim evidence date: undated; source checked: 2026-10-05. https://data.clarionsolutions.ca/canada-data-centres/editions/2026-10-06-83c11c799ab4-public-2026-10-07/records/bc-telus-georgia150/#claim-pub-bc-telus-georgia150-review-3
Cite the linked primary evidence as well. Publication and access dates do not establish current operations.
Cooling
PlannedThe Vancouver developments are designed for liquid recirculation and future district heat reuse. The release does not establish installed or commissioned systems.
- Evidence date
- Undated source
- Checked
- 2026-10-05
- Scope
- Vancouver projects
- Evidence type
- Reported
- Status describes
- Cooling system at stated scope
- TELUS and Government of Canada advance work to scale Canada's sovereign AI infrastructure · Issuer press release via CNW
- Allied Reports Q4 and Full-Year Results; Announces Leadership Update and Equity Financing · Allied Properties REIT
- CD-1 (818) - 720 Beatty Street and 701 Expo Boulevard · City of Vancouver
Permanent claim link · Claim pub-bc-telus-georgia150-review-4
Citation text (select to copy)
Clarion Solutions. TELUS / Westbank 150 West Georgia AI Factory. Canadian Data Centre Atlas. Record bc-telus-georgia150; claim pub-bc-telus-georgia150-review-4. Edition 2026-10-06-83c11c799ab4-public-2026-10-07 (publication date: 2026-10-07); evidence review through 2026-10-06. Claim evidence date: undated; source checked: 2026-10-05. https://data.clarionsolutions.ca/canada-data-centres/editions/2026-10-06-83c11c799ab4-public-2026-10-07/records/bc-telus-georgia150/#claim-pub-bc-telus-georgia150-review-4
Cite the linked primary evidence as well. Publication and access dates do not establish current operations.
Hardware
PlannedGrace Blackwell and Vera Rubin platforms and more than 60,000 GPUs are a full-cluster plan. The release does not allocate a model/count to this site or establish installation.
- Evidence date
- Undated source
- Checked
- 2026-10-05
- Scope
- Three site cluster
- Evidence type
- Reported
- Status describes
- Hardware deployment procurement or support
- TELUS and Government of Canada advance work to scale Canada's sovereign AI infrastructure · Issuer press release via CNW
- Allied Reports Q4 and Full-Year Results; Announces Leadership Update and Equity Financing · Allied Properties REIT
- CD-1 (818) - 720 Beatty Street and 701 Expo Boulevard · City of Vancouver
Permanent claim link · Claim pub-bc-telus-georgia150-review-5
Citation text (select to copy)
Clarion Solutions. TELUS / Westbank 150 West Georgia AI Factory. Canadian Data Centre Atlas. Record bc-telus-georgia150; claim pub-bc-telus-georgia150-review-5. Edition 2026-10-06-83c11c799ab4-public-2026-10-07 (publication date: 2026-10-07); evidence review through 2026-10-06. Claim evidence date: undated; source checked: 2026-10-05. https://data.clarionsolutions.ca/canada-data-centres/editions/2026-10-06-83c11c799ab4-public-2026-10-07/records/bc-telus-georgia150/#claim-pub-bc-telus-georgia150-review-5
Cite the linked primary evidence as well. Publication and access dates do not establish current operations.
Lifecycle
Zoning permittedThe city’s CD-1(818) zoning permits bulk-data-storage use subject to development conditions. Zoning is not final AI-building construction approval.
- Evidence date
- 2024-02-27
- Checked
- 2026-10-05
- Scope
- Facility
- Evidence type
- Reported
- Status describes
- Facility or project lifecycle
- TELUS and Government of Canada advance work to scale Canada's sovereign AI infrastructure · Issuer press release via CNW
- Allied Reports Q4 and Full-Year Results; Announces Leadership Update and Equity Financing · Allied Properties REIT
- CD-1 (818) - 720 Beatty Street and 701 Expo Boulevard · City of Vancouver
Permanent claim link · Claim pub-bc-telus-georgia150-review-6
Citation text (select to copy)
Clarion Solutions. TELUS / Westbank 150 West Georgia AI Factory. Canadian Data Centre Atlas. Record bc-telus-georgia150; claim pub-bc-telus-georgia150-review-6. Edition 2026-10-06-83c11c799ab4-public-2026-10-07 (publication date: 2026-10-07); evidence review through 2026-10-06. Claim evidence date: 2024-02-27; source checked: 2026-10-05. https://data.clarionsolutions.ca/canada-data-centres/editions/2026-10-06-83c11c799ab4-public-2026-10-07/records/bc-telus-georgia150/#claim-pub-bc-telus-georgia150-review-6
Cite the linked primary evidence as well. Publication and access dates do not establish current operations.
Capacity
Issuer reportedAllied reports 39 MW committed by BC Hydro, a path toward 50 MW and possible scale to 100 MW. Only the first is described as committed, and no utility-signed agreement or energization certificate was independently reviewed.
- Evidence date
- 2026-02-10
- Checked
- 2026-10-05
- Scope
- Facility
- Evidence type
- Reported
- Status describes
- Capacity at stated basis and scope
- Quantity type
- Utility supply
- Basis
- contracted
- TELUS and Government of Canada advance work to scale Canada's sovereign AI infrastructure · Issuer press release via CNW
- Allied Reports Q4 and Full-Year Results; Announces Leadership Update and Equity Financing · Allied Properties REIT
- CD-1 (818) - 720 Beatty Street and 701 Expo Boulevard · City of Vancouver
Permanent claim link · Claim pub-bc-telus-georgia150-review-7
Citation text (select to copy)
Clarion Solutions. TELUS / Westbank 150 West Georgia AI Factory. Canadian Data Centre Atlas. Record bc-telus-georgia150; claim pub-bc-telus-georgia150-review-7. Edition 2026-10-06-83c11c799ab4-public-2026-10-07 (publication date: 2026-10-07); evidence review through 2026-10-06. Claim evidence date: 2026-02-10; source checked: 2026-10-05. https://data.clarionsolutions.ca/canada-data-centres/editions/2026-10-06-83c11c799ab4-public-2026-10-07/records/bc-telus-georgia150/#claim-pub-bc-telus-georgia150-review-7
Cite the linked primary evidence as well. Publication and access dates do not establish current operations.
Ownership
ReportedAllied’s February release extended the Westbank loan to 31 December 2026 and described a possible majority sale while retaining an interest. It did not announce a completed property sale.
- Evidence date
- 2026-02-10
- Checked
- 2026-10-05
- Scope
- Facility
- Evidence type
- Reported
- Status describes
- Ownership operator or developer relationship
- TELUS and Government of Canada advance work to scale Canada's sovereign AI infrastructure · Issuer press release via CNW
- Allied Reports Q4 and Full-Year Results; Announces Leadership Update and Equity Financing · Allied Properties REIT
- CD-1 (818) - 720 Beatty Street and 701 Expo Boulevard · City of Vancouver
Permanent claim link · Claim pub-bc-telus-georgia150-review-8
Citation text (select to copy)
Clarion Solutions. TELUS / Westbank 150 West Georgia AI Factory. Canadian Data Centre Atlas. Record bc-telus-georgia150; claim pub-bc-telus-georgia150-review-8. Edition 2026-10-06-83c11c799ab4-public-2026-10-07 (publication date: 2026-10-07); evidence review through 2026-10-06. Claim evidence date: 2026-02-10; source checked: 2026-10-05. https://data.clarionsolutions.ca/canada-data-centres/editions/2026-10-06-83c11c799ab4-public-2026-10-07/records/bc-telus-georgia150/#claim-pub-bc-telus-georgia150-review-8
Cite the linked primary evidence as well. Publication and access dates do not establish current operations.
Ownership
ReportedThe reviewed source identifies TELUS / Westbank in the operator or development role. This does not establish title to the underlying land.
- Evidence date
- Undated source
- Checked
- 2026-10-05
- Scope
- Facility
- Evidence type
- Reported
- Status describes
- Ownership operator or developer relationship
- TELUS and Government of Canada advance work to scale Canada's sovereign AI infrastructure · Issuer press release via CNW
- Allied Reports Q4 and Full-Year Results; Announces Leadership Update and Equity Financing · Allied Properties REIT
- CD-1 (818) - 720 Beatty Street and 701 Expo Boulevard · City of Vancouver
Permanent claim link · Claim pub-bc-telus-georgia150-review-9
Citation text (select to copy)
Clarion Solutions. TELUS / Westbank 150 West Georgia AI Factory. Canadian Data Centre Atlas. Record bc-telus-georgia150; claim pub-bc-telus-georgia150-review-9. Edition 2026-10-06-83c11c799ab4-public-2026-10-07 (publication date: 2026-10-07); evidence review through 2026-10-06. Claim evidence date: undated; source checked: 2026-10-05. https://data.clarionsolutions.ca/canada-data-centres/editions/2026-10-06-83c11c799ab4-public-2026-10-07/records/bc-telus-georgia150/#claim-pub-bc-telus-georgia150-review-9
Cite the linked primary evidence as well. Publication and access dates do not establish current operations.