Crusoe / KALiNA Alsike Energy Park

Crusoe / KALiNA Distributed Power · Alberta (municipality unverified), Alberta

Record ab-crusoe-alsike · 2026-10-06-83c11c799ab4-public-2026-10-06

Historical published edition. Do not treat these as newer or additional facts. Evidence reviewed through 2026-10-06. Edition publication date: 2026-10-06.

Research record, not a building count. Campus and phase overlap may exist; do not add capacity values.

Current record profile · This edition’s record JSON · Edition overview

Identity provenance

Location

Reported

Alberta (municipality unverified), Alberta. City or regional reference only; no facility coordinates are published.

Evidence date
Undated source
Checked
2026-10-05
Scope
Facility
Evidence type
Reported
Status describes
Published location reference
Citation text (select to copy)

Clarion Solutions. Crusoe / KALiNA Alsike Energy Park. Canadian Data Centre Atlas. Record ab-crusoe-alsike; claim pub-ab-crusoe-alsike-review-1. Edition 2026-10-06-83c11c799ab4-public-2026-10-06 (publication date: 2026-10-06); evidence review through 2026-10-06. Claim evidence date: undated; source checked: 2026-10-05. https://data.clarionsolutions.ca/canada-data-centres/editions/2026-10-06-83c11c799ab4-public-2026-10-06/records/ab-crusoe-alsike/#claim-pub-ab-crusoe-alsike-review-1

Cite the linked primary evidence as well. Publication and access dates do not establish current operations.

Lifecycle

Proposed

The February 2025 framework contemplated joint AI-data-centre development at Alsike Energy Park. It did not establish a completed site-specific development agreement or construction start.

Evidence date
2025-02-12
Checked
2026-10-05
Scope
Facility
Evidence type
Reported
Status describes
Facility or project lifecycle
Citation text (select to copy)

Clarion Solutions. Crusoe / KALiNA Alsike Energy Park. Canadian Data Centre Atlas. Record ab-crusoe-alsike; claim pub-ab-crusoe-alsike-review-2. Edition 2026-10-06-83c11c799ab4-public-2026-10-06 (publication date: 2026-10-06); evidence review through 2026-10-06. Claim evidence date: 2025-02-12; source checked: 2026-10-05. https://data.clarionsolutions.ca/canada-data-centres/editions/2026-10-06-83c11c799ab4-public-2026-10-06/records/ab-crusoe-alsike/#claim-pub-ab-crusoe-alsike-review-2

Cite the linked primary evidence as well. Publication and access dates do not establish current operations.

Capacity

Proposed

The initial power concept used a 170 MW gas-fired plant. This is generation capacity, not a stated IT-load figure.

Evidence date
2025-02-12
Checked
2026-10-05
Scope
Facility
Evidence type
Reported
Status describes
Capacity at stated basis and scope
Quantity type
Generation
Basis
proposed
Reported quantity
170 MW
Citation text (select to copy)

Clarion Solutions. Crusoe / KALiNA Alsike Energy Park. Canadian Data Centre Atlas. Record ab-crusoe-alsike; claim pub-ab-crusoe-alsike-review-3. Edition 2026-10-06-83c11c799ab4-public-2026-10-06 (publication date: 2026-10-06); evidence review through 2026-10-06. Claim evidence date: 2025-02-12; source checked: 2026-10-05. https://data.clarionsolutions.ca/canada-data-centres/editions/2026-10-06-83c11c799ab4-public-2026-10-06/records/ab-crusoe-alsike/#claim-pub-ab-crusoe-alsike-review-3

Cite the linked primary evidence as well. Publication and access dates do not establish current operations.

Power

Planned

The concept couples natural-gas generation and carbon capture with minimum 15-year power-purchase agreements, subject to further project agreements.

Evidence date
2025-02-12
Checked
2026-10-05
Scope
Facility
Evidence type
Reported
Status describes
Power supply or backup configuration
Citation text (select to copy)

Clarion Solutions. Crusoe / KALiNA Alsike Energy Park. Canadian Data Centre Atlas. Record ab-crusoe-alsike; claim pub-ab-crusoe-alsike-review-4. Edition 2026-10-06-83c11c799ab4-public-2026-10-06 (publication date: 2026-10-06); evidence review through 2026-10-06. Claim evidence date: 2025-02-12; source checked: 2026-10-05. https://data.clarionsolutions.ca/canada-data-centres/editions/2026-10-06-83c11c799ab4-public-2026-10-06/records/ab-crusoe-alsike/#claim-pub-ab-crusoe-alsike-review-4

Cite the linked primary evidence as well. Publication and access dates do not establish current operations.

Commercial

Framework

The framework anticipated later project-development agreements and power contracts; an executed site-specific offtake is not established.

Evidence date
2025-02-12
Checked
2026-10-05
Scope
Facility
Evidence type
Reported
Status describes
Commercial disclosure or relationship
Citation text (select to copy)

Clarion Solutions. Crusoe / KALiNA Alsike Energy Park. Canadian Data Centre Atlas. Record ab-crusoe-alsike; claim pub-ab-crusoe-alsike-review-5. Edition 2026-10-06-83c11c799ab4-public-2026-10-06 (publication date: 2026-10-06); evidence review through 2026-10-06. Claim evidence date: 2025-02-12; source checked: 2026-10-05. https://data.clarionsolutions.ca/canada-data-centres/editions/2026-10-06-83c11c799ab4-public-2026-10-06/records/ab-crusoe-alsike/#claim-pub-ab-crusoe-alsike-review-5

Cite the linked primary evidence as well. Publication and access dates do not establish current operations.

Ownership

Reported

The reviewed source identifies Crusoe / KALiNA Distributed Power in the operator or development role. This does not establish title to the underlying land.

Evidence date
Undated source
Checked
2026-10-05
Scope
Facility
Evidence type
Reported
Status describes
Ownership operator or developer relationship
Citation text (select to copy)

Clarion Solutions. Crusoe / KALiNA Alsike Energy Park. Canadian Data Centre Atlas. Record ab-crusoe-alsike; claim pub-ab-crusoe-alsike-review-6. Edition 2026-10-06-83c11c799ab4-public-2026-10-06 (publication date: 2026-10-06); evidence review through 2026-10-06. Claim evidence date: undated; source checked: 2026-10-05. https://data.clarionsolutions.ca/canada-data-centres/editions/2026-10-06-83c11c799ab4-public-2026-10-06/records/ab-crusoe-alsike/#claim-pub-ab-crusoe-alsike-review-6