Version-specific research record
Vantage Montréal III / QC61
Vantage Data Centers · Montréal area (municipality unverified), Quebec
Record QC-VANTAGE-QC6 · 2026-10-06-83c11c799ab4-public-2026-10-06
Historical published edition. Do not treat these as newer or additional facts. Evidence reviewed through 2026-10-06. Edition publication date: 2026-10-06.
Research record, not a building count. Campus and phase overlap may exist; do not add capacity values.
Current record profile · This edition’s record JSON · Edition overview
Identity provenance
Location
ReportedRevenco identifies Vantage’s Montréal III/QC61 project on Montréal island.
- Evidence date
- Undated source
- Checked
- 2026-10-05
- Scope
- Facility
- Evidence type
- Reported
- Status describes
- Published location reference
Permanent claim link · Claim pub-quebec-east-QC-VANTAGE-QC6-1
Citation text (select to copy)
Clarion Solutions. Vantage Montréal III / QC61. Canadian Data Centre Atlas. Record QC-VANTAGE-QC6; claim pub-quebec-east-QC-VANTAGE-QC6-1. Edition 2026-10-06-83c11c799ab4-public-2026-10-06 (publication date: 2026-10-06); evidence review through 2026-10-06. Claim evidence date: undated; source checked: 2026-10-05. https://data.clarionsolutions.ca/canada-data-centres/editions/2026-10-06-83c11c799ab4-public-2026-10-06/records/QC-VANTAGE-QC6/#claim-pub-quebec-east-QC-VANTAGE-QC6-1
Cite the linked primary evidence as well. Publication and access dates do not establish current operations.
Capacity
Planned full buildoutRevenco describes full deployment as two 15 MW modules, totalling 30 MW of computing capacity.
- Evidence date
- Undated source
- Checked
- 2026-10-05
- Scope
- Facility
- Evidence type
- Reported
- Status describes
- Reported capacity
- Quantity type
- It load
- Basis
- contractor computing-capacity design; full commissioning not established
- Reported quantity
- 30 MW
Permanent claim link · Claim pub-quebec-east-QC-VANTAGE-QC6-2
Citation text (select to copy)
Clarion Solutions. Vantage Montréal III / QC61. Canadian Data Centre Atlas. Record QC-VANTAGE-QC6; claim pub-quebec-east-QC-VANTAGE-QC6-2. Edition 2026-10-06-83c11c799ab4-public-2026-10-06 (publication date: 2026-10-06); evidence review through 2026-10-06. Claim evidence date: undated; source checked: 2026-10-05. https://data.clarionsolutions.ca/canada-data-centres/editions/2026-10-06-83c11c799ab4-public-2026-10-06/records/QC-VANTAGE-QC6/#claim-pub-quebec-east-QC-VANTAGE-QC6-2
Cite the linked primary evidence as well. Publication and access dates do not establish current operations.
Power
Project descriptionRevenco describes planned near-total renewable electricity from Hydro-Québec.
- Evidence date
- Undated source
- Checked
- 2026-10-05
- Scope
- Facility
- Evidence type
- Reported
- Status describes
- Power configuration
Permanent claim link · Claim pub-quebec-east-QC-VANTAGE-QC6-3
Citation text (select to copy)
Clarion Solutions. Vantage Montréal III / QC61. Canadian Data Centre Atlas. Record QC-VANTAGE-QC6; claim pub-quebec-east-QC-VANTAGE-QC6-3. Edition 2026-10-06-83c11c799ab4-public-2026-10-06 (publication date: 2026-10-06); evidence review through 2026-10-06. Claim evidence date: undated; source checked: 2026-10-05. https://data.clarionsolutions.ca/canada-data-centres/editions/2026-10-06-83c11c799ab4-public-2026-10-06/records/QC-VANTAGE-QC6/#claim-pub-quebec-east-QC-VANTAGE-QC6-3
Cite the linked primary evidence as well. Publication and access dates do not establish current operations.