Urbacon Data Centre Solutions · Montréal, Quebec

Record QC-URBACON-MTL · 2026-10-06-83c11c799ab4-public-2026-10-06

Historical published edition. Do not treat these as newer or additional facts. Evidence reviewed through 2026-10-06. Edition publication date: 2026-10-06.

Research record, not a building count. Campus and phase overlap may exist; do not add capacity values.

Current record profile · This edition’s record JSON · Edition overview

Identity provenance

Location

Reported

Urbacon identifies its purpose-built Downtown Montréal Data Centre on rue de l’Inspecteur.

Evidence date
Undated source
Checked
2026-10-05
Scope
Facility
Evidence type
Reported
Status describes
Published location reference
Citation text (select to copy)

Clarion Solutions. Downtown Montréal Data Centre. Canadian Data Centre Atlas. Record QC-URBACON-MTL; claim pub-quebec-east-QC-URBACON-MTL-1. Edition 2026-10-06-83c11c799ab4-public-2026-10-06 (publication date: 2026-10-06); evidence review through 2026-10-06. Claim evidence date: undated; source checked: 2026-10-05. https://data.clarionsolutions.ca/canada-data-centres/editions/2026-10-06-83c11c799ab4-public-2026-10-06/records/QC-URBACON-MTL/#claim-pub-quebec-east-QC-URBACON-MTL-1

Cite the linked primary evidence as well. Publication and access dates do not establish current operations.

Capacity

Reported

Urbacon’s technical panel states 20 MW of critical power.

Evidence date
Undated source
Checked
2026-10-05
Scope
Facility
Evidence type
Reported
Status describes
Reported capacity
Quantity type
Critical power
Basis
undated operator technical panel; not measured demand or available space
Reported quantity
20 MW · Same page has an unreconciled 21 MW headline.
Citation text (select to copy)

Clarion Solutions. Downtown Montréal Data Centre. Canadian Data Centre Atlas. Record QC-URBACON-MTL; claim pub-quebec-east-QC-URBACON-MTL-2. Edition 2026-10-06-83c11c799ab4-public-2026-10-06 (publication date: 2026-10-06); evidence review through 2026-10-06. Claim evidence date: undated; source checked: 2026-10-05. https://data.clarionsolutions.ca/canada-data-centres/editions/2026-10-06-83c11c799ab4-public-2026-10-06/records/QC-URBACON-MTL/#claim-pub-quebec-east-QC-URBACON-MTL-2

Cite the linked primary evidence as well. Publication and access dates do not establish current operations.

Cooling

Reported

Urbacon describes hydroelectric grid power, ambient cooling and configurable hall-level cooling redundancy.

Evidence date
Undated source
Checked
2026-10-05
Scope
Facility
Evidence type
Reported
Status describes
Cooling configuration
Citation text (select to copy)

Clarion Solutions. Downtown Montréal Data Centre. Canadian Data Centre Atlas. Record QC-URBACON-MTL; claim pub-quebec-east-QC-URBACON-MTL-3. Edition 2026-10-06-83c11c799ab4-public-2026-10-06 (publication date: 2026-10-06); evidence review through 2026-10-06. Claim evidence date: undated; source checked: 2026-10-05. https://data.clarionsolutions.ca/canada-data-centres/editions/2026-10-06-83c11c799ab4-public-2026-10-06/records/QC-URBACON-MTL/#claim-pub-quebec-east-QC-URBACON-MTL-3

Cite the linked primary evidence as well. Publication and access dates do not establish current operations.

Connectivity

Reported

Urbacon advertises a carrier-neutral design with three separate fibre entrance rooms; end-to-end route diversity is not independently verified.

Evidence date
Undated source
Checked
2026-10-05
Scope
Facility
Evidence type
Reported
Status describes
Connectivity service or plan
Citation text (select to copy)

Clarion Solutions. Downtown Montréal Data Centre. Canadian Data Centre Atlas. Record QC-URBACON-MTL; claim pub-quebec-east-QC-URBACON-MTL-4. Edition 2026-10-06-83c11c799ab4-public-2026-10-06 (publication date: 2026-10-06); evidence review through 2026-10-06. Claim evidence date: undated; source checked: 2026-10-05. https://data.clarionsolutions.ca/canada-data-centres/editions/2026-10-06-83c11c799ab4-public-2026-10-06/records/QC-URBACON-MTL/#claim-pub-quebec-east-QC-URBACON-MTL-4

Cite the linked primary evidence as well. Publication and access dates do not establish current operations.