CLARION Data projects

Browse this record in the Atlas

Project · Evidence reviewed 2026-10-06

BUZZ acquired Toronto data-centre conversion

BUZZ High Performance Computing / HIVE · Toronto, Ontario

Research record, not a building count. Campus and phase overlap may exist; do not add capacity values. Access dates do not establish fresh commissioning.

Identity and map provenance

City reference only; not the facility. Derived city center, rounded to four decimals. The marker is not a building, entrance, campus or parcel location. GeoNames 6167865 · CC BY 4.0

Lifecycle

Conversion planned

HIVE announced completion of a Toronto data-centre acquisition through BUZZ on September 17, 2025, with a planned Tier 1-to-Tier 3 upgrade. AI commissioning is not established.

Evidence date
2025-09-17
Checked
2026-10-05
Scope
Facility
Evidence type
Reported
Status describes
Facility or project lifecycle

Capacity

Installed

The acquisition release describes a 7.2 MW facility. This is acquisition-stage facility capacity, not demonstrated usable AI IT load.

Evidence date
2025-09-17
Checked
2026-10-05
Scope
Facility
Evidence type
Reported
Status describes
Capacity at stated basis and scope
Quantity type
Facility power unspecified
Basis
acquisition disclosure; IT basis not established
Reported quantity
7.2 MW