CLARION Data projects

Browse this record in the Atlas

Project · Evidence reviewed 2026-10-06

Algoma Data Center

Red Jar Algoma Data Center Corp. · Undisclosed, Ontario

Research record, not a building count. Campus and phase overlap may exist; do not add capacity values. Source reuse notice: Copyright © 2004-2022 Independent Electricity System Operator, all rights reserved. This information is subject to the Terms of Use set out in the IESO’s website (www.ieso.ca) Access dates do not establish fresh commissioning.

Identity and map provenance

No unique reviewed city reference. Intentionally unpinned.

Power readiness

Active

The IESO table lists the Algoma Data Center connection application as Active. This is an assessment/application status, not a facility-operation or energization finding.

Evidence date
2026-09-10
Checked
2026-10-05
Scope
Connection application
Evidence type
Reported
Status describes
Utility connection application status

Capacity

Proposed

The application requests 400 MW of load with proposed in-service timing 2029-Q4. The value is proposed grid load, not operating IT capacity.

Evidence date
2026-09-10
Checked
2026-10-05
Scope
Connection application
Evidence type
Reported
Status describes
Capacity at stated basis and scope
Quantity type
Utility supply
Basis
proposed connection application load
Reported quantity
400 MW
  • Public connection application status table · Independent Electricity System Operator

    Copyright © 2004-2022 Independent Electricity System Operator, all rights reserved. This information is subject to the Terms of Use set out in the IESO’s website (www.ieso.ca) Source terms

Location

Reported

The registry places the application in Ontario’s Northeast transmission zone; the row does not establish a parcel or municipality.

Evidence date
2026-09-10
Checked
2026-10-05
Scope
Connection application
Evidence type
Reported
Status describes
Published location reference
  • Public connection application status table · Independent Electricity System Operator

    Copyright © 2004-2022 Independent Electricity System Operator, all rights reserved. This information is subject to the Terms of Use set out in the IESO’s website (www.ieso.ca) Source terms

Ownership

Reported

Red Jar Algoma Data Center Corp. is the connection applicant; the row does not establish land ownership or a commissioned facility operator.

Evidence date
2026-09-10
Checked
2026-10-05
Scope
Connection application
Evidence type
Reported
Status describes
Ownership operator or developer relationship
  • Public connection application status table · Independent Electricity System Operator

    Copyright © 2004-2022 Independent Electricity System Operator, all rights reserved. This information is subject to the Terms of Use set out in the IESO’s website (www.ieso.ca) Source terms