Facility · Evidence reviewed 2026-10-06
Equinix TR2
Equinix · Toronto, Ontario
Research record, not a building count. Campus and phase overlap may exist; do not add capacity values. Access dates do not establish fresh commissioning.
Identity and map provenance
- Name: Smith + Andersen, Symtech
- Operator: Smith + Andersen, Symtech
- Province: Smith + Andersen, Symtech
- City: Smith + Andersen, Symtech
- Record kind: Smith + Andersen, Symtech
- Disposition: Smith + Andersen, Symtech
City reference only; not the facility. Derived city center, rounded to four decimals. The marker is not a building, entrance, campus or parcel location. GeoNames 6167865 · CC BY 4.0
Lifecycle
HistoricalSmith + Andersen identifies Equinix TR2 as a Toronto project completed in 2015; Symtech locates it at 45 Parliament Street.
- Evidence date
- 2015
- Checked
- 2026-10-05
- Scope
- Facility
- Evidence type
- Reported
- Status describes
- Facility or project lifecycle
- EQUINIX IBX DATA CENTER: TR2 · Smith + Andersen
- Equinix TR2 - Symtech · Symtech
Capacity
DesignThe engineer describes a 16 MW maximum building design connected to Toronto Hydro. This is a design figure, not currently usable IT capacity; a separate developer source uses MVA and is not numerically equated.
- Evidence date
- 2015
- Checked
- 2026-10-05
- Scope
- Facility
- Evidence type
- Reported
- Status describes
- Capacity at stated basis and scope
- Quantity type
- Building design power
- Basis
- engineer maximum design
- Reported quantity
- 16 MW
- EQUINIX IBX DATA CENTER: TR2 · Smith + Andersen
Power
HistoricalThe engineer’s 2015 account specifies seven 2.5 MW diesel generators and 2N critical distribution. Symtech’s phase-two account describes adding one 2.5 MW unit; these scopes are not added together.
- Evidence date
- 2015
- Checked
- 2026-10-05
- Scope
- Facility
- Evidence type
- Reported
- Status describes
- Power supply or backup configuration
- EQUINIX IBX DATA CENTER: TR2 · Smith + Andersen
- Equinix TR2 - Symtech · Symtech
Cooling
HistoricalThe engineer specifies over 3,000 tons of magnetic-bearing chiller cooling with free-cooling cycles; Symtech describes overhead cooling for its phase.
- Evidence date
- 2015
- Checked
- 2026-10-05
- Scope
- Facility
- Evidence type
- Reported
- Status describes
- Cooling system at stated scope
- EQUINIX IBX DATA CENTER: TR2 · Smith + Andersen
- Equinix TR2 - Symtech · Symtech