CLARION Data projects

Browse this record in the Atlas

Facility · Evidence reviewed 2026-10-06

BlockLAB Wabush data centre

BlockLAB · Wabush, Newfoundland and Labrador

Research record, not a building count. Campus and phase overlap may exist; do not add capacity values. Access dates do not establish fresh commissioning.

Identity and map provenance

City reference only; not the facility. Derived city center, rounded to four decimals. The marker is not a building, entrance, campus or parcel location. GeoNames 6174844 · CC BY 4.0

Lifecycle

Historical

North Star Associates describes engineering, construction management and commissioning for BlockLAB’s Wabush project during 2018–2020.

Evidence date
Undated source
Checked
2026-10-05
Scope
Facility
Evidence type
Reported
Status describes
Facility or project lifecycle

Capacity

Historical

The contractor describes the Wabush site as 20 MW.

Evidence date
Undated source
Checked
2026-10-05
Scope
Facility
Evidence type
Reported
Status describes
Reported capacity
Quantity type
Unspecified
Basis
contractor-reported design-build rating; gross-versus-IT basis not stated
Reported quantity
20 MW

Power

Historical

The contractor describes Labrador hydroelectric generation as a project advantage; no exclusive physical supply or site-specific utility contract is established.

Evidence date
Undated source
Checked
2026-10-05
Scope
Facility
Evidence type
Reported
Status describes
Power configuration