CLARION Data projects

Browse this record in the Atlas

Project · Evidence reviewed 2026-10-06

Hillside AI Centre at TRU

TrueNorth Sustainable Infrastructure / Bell Canada · Kamloops, British Columbia

Research record, not a building count. Campus and phase overlap may exist; do not add capacity values. Access dates do not establish fresh commissioning.

Identity and map provenance

City reference only; not the facility. Derived city center, rounded to four decimals. The marker is not a building, entrance, campus or parcel location. GeoNames 5989045 · CC BY 4.0

Location

Reported

Kamloops, British Columbia. City or regional reference only; no facility coordinates are published.

Evidence date
Undated source
Checked
2026-10-05
Scope
Facility
Evidence type
Reported
Status describes
Published location reference

Lifecycle

Under construction

TRU’s April 2026 announcement says construction has started at Hillside, with operation anticipated in late 2027. Older developer design-stage text is not treated as the latest milestone.

Evidence date
2026-04-09
Checked
2026-10-05
Scope
Facility
Evidence type
Reported
Status describes
Facility or project lifecycle

Capacity

Planned

TrueNorth describes 27 MW expected power delivery for Hillside. It remains a design/development figure, not established operating IT capacity.

Evidence date
Undated source
Checked
2026-10-05
Scope
Facility
Evidence type
Reported
Status describes
Capacity at stated basis and scope
Quantity type
Utility supply
Basis
proposed
Reported quantity
27 MW · Separate source-reported quantities are not additive.

Power

Planned

TRU describes BC Hydro hydroelectric supply; an executed connection agreement and energization date are not established.

Evidence date
Undated source
Checked
2026-10-05
Scope
Facility
Evidence type
Reported
Status describes
Power supply or backup configuration

Cooling

Planned

The project describes closed-loop cooling and potential future campus heat recovery. The future district-energy connection is not counted as installed reuse.

Evidence date
Undated source
Checked
2026-10-05
Scope
Facility
Evidence type
Reported
Status describes
Cooling system at stated scope

Ownership

Leased

TRU Community Trust identifies university land leased to TrueNorth, with the facility intended to join Bell AI Fabric. This separates land, developer and planned operating roles.

Evidence date
2026-04-09
Checked
2026-10-05
Scope
Facility
Evidence type
Reported
Status describes
Ownership operator or developer relationship

Ownership

Reported

The reviewed source identifies TrueNorth Sustainable Infrastructure / Bell Canada in the operator or development role. This does not establish title to the underlying land.

Evidence date
Undated source
Checked
2026-10-05
Scope
Facility
Evidence type
Reported
Status describes
Ownership operator or developer relationship