Project · Evidence reviewed 2026-10-06
Boreal Technology Hub / Keephills data centre development
Brookfield / CPP Investments; TransAlta site and power provider · Parkland County, Alberta
Research record, not a building count. Campus and phase overlap may exist; do not add capacity values. Access dates do not establish fresh commissioning.
Identity and map provenance
- Name: Boreal Technology Hub / BGRE
- Operator: Boreal Technology Hub / BGRE
- Province: Boreal Technology Hub / BGRE
- City: Boreal Technology Hub / BGRE
- Record kind: Boreal Technology Hub / BGRE
- Disposition: Boreal Technology Hub / BGRE
No unique reviewed city reference. Intentionally unpinned.
Location
ReportedParkland County, Alberta. City or regional reference only; no facility coordinates are published.
- Evidence date
- Undated source
- Checked
- 2026-10-05
- Scope
- Facility
- Evidence type
- Reported
- Status describes
- Published location reference
- Boreal · Boreal Technology Hub / BGRE
Lifecycle
ProposedThe project team describes Boreal as a proposed data-processing development under the February 2026 Brookfield/CPP/TransAlta memorandum. Construction and a completed operating facility are not established.
- Evidence date
- Undated source
- Checked
- 2026-10-05
- Scope
- Facility
- Evidence type
- Reported
- Status describes
- Facility or project lifecycle
- Boreal · Boreal Technology Hub / BGRE
Capacity
Allocated not energizedThe current project page states an initial 230 MW allocation under AESO’s first large-load phase. This is a proponent-reported allocation, not verified energized IT load.
- Evidence date
- Undated source
- Checked
- 2026-10-05
- Scope
- Phase
- Evidence type
- Reported
- Status describes
- Capacity at stated basis and scope
- Quantity type
- Utility allocation
- Basis
- proponent_reported_allocation_not_energized
- Reported quantity
- 230 MW · Separate source-reported quantities are not additive.
- Boreal · Boreal Technology Hub / BGRE
Power
PlannedThe project team says TransAlta will provide the site and power. The final data-centre backup and physical supply configuration is not disclosed.
- Evidence date
- Undated source
- Checked
- 2026-10-05
- Scope
- Facility
- Evidence type
- Reported
- Status describes
- Power supply or backup configuration
- Boreal · Boreal Technology Hub / BGRE
Ownership
ReportedThe reviewed source identifies Brookfield / CPP Investments; TransAlta site and power provider in the operator or development role. This does not establish title to the underlying land.
- Evidence date
- Undated source
- Checked
- 2026-10-05
- Scope
- Facility
- Evidence type
- Reported
- Status describes
- Ownership operator or developer relationship
- Boreal · Boreal Technology Hub / BGRE