HubOne AI & BTC High Density Compute Park / NRG Hub-1

HubOne · Calgary region, Alberta

Research record, not a building count. Campus and phase overlap may exist; do not add capacity values. Access dates do not establish fresh commissioning.

Identity and map provenance

No unique reviewed city reference. Intentionally unpinned.

Location

Reported

Calgary region, Alberta. City or regional reference only; no facility coordinates are published.

Evidence date
Undated source
Checked
2026-10-05
Scope
Facility
Evidence type
Reported
Status describes
Published location reference

Lifecycle

Proposed

HubOne markets a proposed gas-to-compute campus east of Calgary; its power-delivery timetable is not proof of commissioning.

Evidence date
Undated source
Checked
2026-10-05
Scope
Facility
Evidence type
Reported
Status describes
Facility or project lifecycle

Capacity

Marketed future

The sponsor’s undated roadmap claims up to 600 MW by 2026, more than 3,000 MW by 2028 and possible scale to 7,000 MW. These are non-additive power-development ambitions, not verified IT capacity.

Evidence date
Undated source
Checked
2026-10-05
Scope
Phase
Evidence type
Reported
Status describes
Capacity at stated basis and scope
Quantity type
Generation
Basis
proposed

Power

Planned

The concept combines baseload gas with renewable power imported from other generation sites. It does not establish installed equipment at Hub-1.

Evidence date
Undated source
Checked
2026-10-05
Scope
Facility
Evidence type
Reported
Status describes
Power supply or backup configuration

Cooling

Planned

High-density immersion cooling is proposed for the mining component; an installed AI cooling design is not established.

Evidence date
Undated source
Checked
2026-10-05
Scope
Facility
Evidence type
Reported
Status describes
Cooling system at stated scope

Hardware

Marketed

The sponsor markets an Ultra Blackwell cluster concept, without a verified GPU model, installed count or executed order.

Evidence date
Undated source
Checked
2026-10-05
Scope
Facility
Evidence type
Reported
Status describes
Hardware deployment procurement or support

Connectivity

Planned

A dedicated fibre ring is described as under development; live carriers and physical paths are not demonstrated.

Evidence date
Undated source
Checked
2026-10-05
Scope
Facility
Evidence type
Reported
Status describes
Connectivity infrastructure or service

Commercial

Marketed

The sponsor offers long-duration power-purchase terms and invites contracting; no executed customer contract is established.

Evidence date
Undated source
Checked
2026-10-05
Scope
Facility
Evidence type
Reported
Status describes
Commercial disclosure or relationship

Ownership

Reported

The reviewed source identifies HubOne in the operator or development role. This does not establish title to the underlying land.

Evidence date
Undated source
Checked
2026-10-05
Scope
Facility
Evidence type
Reported
Status describes
Ownership operator or developer relationship