Project · Evidence reviewed 2026-10-06
Genesee data centre co-location opportunity
Capital Power · Leduc County, Alberta
Research record, not a building count. Campus and phase overlap may exist; do not add capacity values. Access dates do not establish fresh commissioning.
Identity and map provenance
- Name: Capital Power, Capital Power
- Operator: Capital Power, Capital Power
- Province: Capital Power, Capital Power
- City: Capital Power, Capital Power
- Record kind: Capital Power, Capital Power
- Disposition: Capital Power, Capital Power
No unique reviewed city reference. Intentionally unpinned.
Location
ReportedLeduc County, Alberta. City or regional reference only; no facility coordinates are published.
- Evidence date
- Undated source
- Checked
- 2026-10-05
- Scope
- Facility
- Evidence type
- Reported
- Status describes
- Published location reference
- Genesee Generating Station - Capital Power · Capital Power
- Data Centres - Capital Power · Capital Power
Lifecycle
Development opportunityCapital Power markets land beside the Genesee generating station for potential data-centre development. An operating power station is not evidence that a data centre has opened.
- Evidence date
- Undated source
- Checked
- 2026-10-05
- Scope
- Facility
- Evidence type
- Reported
- Status describes
- Facility or project lifecycle
- Genesee Generating Station - Capital Power · Capital Power
- Data Centres - Capital Power · Capital Power
Capacity
Marketed futureCapital Power advertises approximately 500 MW for data-centre development by 2028–2029, with potential to scale. This is future supply marketing, not contracted or operating IT load.
- Evidence date
- Undated source
- Checked
- 2026-10-05
- Scope
- Facility
- Evidence type
- Reported
- Status describes
- Capacity at stated basis and scope
- Quantity type
- Future power supply
- Basis
- marketed_future_supply
- Reported quantity
- 500 MW · approximately; available by 2028–2029; not contracted IT
- Genesee Generating Station - Capital Power · Capital Power
- Data Centres - Capital Power · Capital Power
Power
PlannedThe opportunity is associated with Genesee’s natural-gas generation; a final data-centre supply and backup configuration is not disclosed.
- Evidence date
- Undated source
- Checked
- 2026-10-05
- Scope
- Facility
- Evidence type
- Reported
- Status describes
- Power supply or backup configuration
- Genesee Generating Station - Capital Power · Capital Power
- Data Centres - Capital Power · Capital Power
Connectivity
PlanningThe proponent says access to redundant fibre is being explored. This does not establish live circuits or verified diverse routes.
- Evidence date
- Undated source
- Checked
- 2026-10-05
- Scope
- Facility
- Evidence type
- Reported
- Status describes
- Connectivity infrastructure or service
- Genesee Generating Station - Capital Power · Capital Power
- Data Centres - Capital Power · Capital Power
Ownership
ReportedThe reviewed source identifies Capital Power in the operator or development role. This does not establish title to the underlying land.
- Evidence date
- Undated source
- Checked
- 2026-10-05
- Scope
- Facility
- Evidence type
- Reported
- Status describes
- Ownership operator or developer relationship
- Genesee Generating Station - Capital Power · Capital Power
- Data Centres - Capital Power · Capital Power