CLARION Data projects

Browse this record in the Atlas

Facility · Evidence reviewed 2026-10-06

WhiteFiber / Enovum MTL-1

WhiteFiber / Enovum Data Centers · Montréal, Quebec

Research record, not a building count. Campus and phase overlap may exist; do not add capacity values. Access dates do not establish fresh commissioning.

Identity and map provenance

City reference only; not the facility. Derived city center, rounded to four decimals. The marker is not a building, entrance, campus or parcel location. GeoNames 6077243 · CC BY 4.0

Lifecycle

Reported operating

WhiteFiber’s August 2026 filing identifies its leased MTL-1 operation in Montréal, acquired with Enovum in October 2024.

Evidence date
2026-08-12
Checked
2026-10-05
Scope
Facility
Evidence type
Reported
Status describes
Facility or project lifecycle

Capacity

Reported

The filing describes MTL-1 as 4 MW gross.

Evidence date
2026-08-12
Checked
2026-10-05
Scope
Facility
Evidence type
Reported
Status describes
Reported capacity
Quantity type
Facility power
Basis
gross facility rating; not equivalent to IT load or measured demand
Reported quantity
4 MW

Cooling

Reported

WhiteFiber’s MTL-1 page describes hydroelectric supply, raised-floor hot/cold aisles and N+1 cooling; options and service counts are marketing descriptions.

Evidence date
Undated source
Checked
2026-10-05
Scope
Facility
Evidence type
Reported
Status describes
Cooling configuration

Commercial

Historical

The filing states that MTL-1 was fully leased when acquired in October 2024; present vacancy is not established.

Evidence date
2024-10-11
Checked
2026-10-05
Scope
Facility
Evidence type
Reported
Status describes
Commercial disclosure