Project · Evidence reviewed 2026-10-06
QScale Q01 Building B
QScale · Lévis, Quebec
Research record, not a building count. Campus and phase overlap may exist; do not add capacity values. Access dates do not establish fresh commissioning.
Identity and map provenance
City reference only; not the facility. Derived city center, rounded to four decimals. The marker is not a building, entrance, campus or parcel location. GeoNames 6325521 · CC BY 4.0
Location
ReportedQ01 campus, Lévis, Quebec.
- Evidence date
- 2026-06-04
- Checked
- 2026-10-05
- Scope
- Project · Building B
- Evidence type
- Reported
- Status describes
- Published location reference
Lifecycle
Under constructionQScale reported that Building B construction was underway on 4 June 2026.
- Evidence date
- 2026-06-04
- Checked
- 2026-10-05
- Scope
- Project · Building B
- Evidence type
- Reported
- Status describes
- Facility or project lifecycle
Capacity
PlannedQScale plans 60 MW of IT capacity in Building B.
- Evidence date
- 2026-06-04
- Checked
- 2026-10-05
- Scope
- Project · Building B
- Evidence type
- Reported
- Status describes
- Capacity assertion
- Quantity type
- It load
- Basis
- planned IT capacity; not commissioned capacity
- Reported quantity
- 60 MW
Cooling
PlannedThe design supports liquid-cooled racks alongside air-cooled servers.
- Evidence date
- 2026-06-04
- Checked
- 2026-10-05
- Scope
- Project · Building B
- Evidence type
- Reported
- Status describes
- Cooling configuration
Hardware
PlannedQScale describes readiness for NVIDIA GB300-class systems.
- Evidence date
- 2026-06-04
- Checked
- 2026-10-05
- Scope
- Project · Building B
- Evidence type
- Reported
- Status describes
- Hardware readiness