Project · Evidence reviewed 2026-10-06
Microsoft Lévis datacentre connection project
Microsoft · Lévis, Quebec
Research record, not a building count. Campus and phase overlap may exist; do not add capacity values. Access dates do not establish fresh commissioning.
Identity and map provenance
- Name: Hydro-Québec
- Operator: Hydro-Québec
- Province: Hydro-Québec
- City: Hydro-Québec
- Record kind: Hydro-Québec
- Disposition: Hydro-Québec
City reference only; not the facility. Derived city center, rounded to four decimals. The marker is not a building, entrance, campus or parcel location. GeoNames 6325521 · CC BY 4.0
Power readiness
PlannedHydro-Québec’s October 2024 plan identifies a Microsoft datacentre connection in Charny, Lévis, with line construction scheduled for 2026–27 and service in 2027.
- Evidence date
- 2024-10
- Checked
- 2026-10-05
- Scope
- Facility
- Evidence type
- Reported
- Status describes
- Power readiness evidence
- Info-projet · Hydro-Québec